Earned value: is the GMP still safe? (US)

You are the project controls engineer for the construction manager on a five-storey hospital tower in the US, built under a guaranteed maximum price. The lender's monitor questioned last month's earned value report. In five tasks you rebuild it: the right budget, honest progress, the real cost, the outturn against the GMP, and a baseline change that hides nothing.

Start task 1

A steel-frame tower in late autumn: lower floors closed in with brick and sheathing, the top floors still open, a tower crane above.Fictional project
Quenby Falls Medical Center, East Patient TowerOctober 2026 report
Job
East Patient Tower, five storeys, month 7 of 20
Contract
Construction manager at risk with a guaranteed maximum price (GMP)
Method
Earned value by the ANSI/EIA-748 guidelines, in the ERP's Earned Value module
Work in the ERP
5 tasks, about 1 h 25 min

Who hands what to whom

Every arrow is a figure that reaches your desk or leaves it, and the task where that happens.

Comes to you

  • SuperintendentReports progress
    • Physical % completeTask 2
  • Owner's repApproves changes
    • CO-04Task 5
YouProject controls engineer, CM at risk

Goes from you

    • The baselineTask 1
    • The outturnTask 4
    Lender's monitorReads CPI and EAC first
    • Actual costTask 3
    • Rev 2Task 5
    Project executiveSigns the report

The project and the people are fictional. Portraits are generated.

Your route through the job

One monthly report, built in the order a controls engineer builds it. Task 1 is free: in Earned Value you set the baseline.

  1. Measure

    Task 1 · 10 min

    The budget the lender measures you against

    You produce
    The budget at completion
    Document
    Baseline rev 1
    In the ERP
    Earned Value
  2. Measure

    Task 2 · 20 min

    What the October work was worth

    You produce
    October earned value
    Document
    Progress report
    In the ERP
    Earned Value
  3. Measure

    Task 3 · 15 min

    Actual cost is not what accounting booked

    You produce
    Actual cost with accruals
    Document
    Job cost report
    In the ERP
    Earned Value
  4. Forecast

    Task 4 · 20 min

    The outturn, and whether the contingency covers it

    You produce
    Outturn and the GMP overrun
    Document
    Monthly report
    In the ERP
    Earned Value
  5. Change

    Task 5 · 20 min

    Rev 2: what may move into the baseline

    You produce
    Baseline rev 2
    Document
    Change log
    In the ERP
    Earned Value

How one report answers 'is the GMP safe?'

Each step below is one task, in the order the report is built.

ReserveBudget
Task 1BaselineAuthorized work only; reserve and fee outside.
BehindEarned
Task 2Earned valueProgress priced at budget.
AccruedCost
Task 3Actual costCost of the same work, accruals in.
OverrunBudget
Task 4OutturnForecast from performance; contingency first.
New workRev 1
Task 5Rev 2Add real work, keep the variance.

Blue is what the task adds; grey is carried over from before.

In short. Measure against authorized work, earn at budget, cost the same work, forecast from performance, and never re-budget the past.