Course introduction · 3 min
Earned value: is the GMP still safe? (US)
You are the project controls engineer for the construction manager on a five-storey hospital tower in the US, built under a guaranteed maximum price. The lender's monitor questioned last month's earned value report. In five tasks you rebuild it: the right budget, honest progress, the real cost, the outturn against the GMP, and a baseline change that hides nothing.
Fictional project- Job
- East Patient Tower, five storeys, month 7 of 20
- Contract
- Construction manager at risk with a guaranteed maximum price (GMP)
- Method
- Earned value by the ANSI/EIA-748 guidelines, in the ERP's Earned Value module
- Work in the ERP
- 5 tasks, about 1 h 25 min
Who hands what to whom
Every arrow is a figure that reaches your desk or leaves it, and the task where that happens.
Comes to you
- SuperintendentReports progress
- Physical % completeTask 2
- Owner's repApproves changes
- CO-04Task 5
YouProject controls engineer, CM at riskGoes from you
- The baselineTask 1
- The outturnTask 4
- Actual costTask 3
- Rev 2Task 5
The project and the people are fictional. Portraits are generated.
Your route through the job
One monthly report, built in the order a controls engineer builds it. Task 1 is free: in Earned Value you set the baseline.
Measure
Task 1 · 10 min
The budget the lender measures you against
- You produce
- The budget at completion
- Document
- Baseline rev 1
- In the ERP
- Earned Value
Measure
Task 2 · 20 min
What the October work was worth
- You produce
- October earned value
- Document
- Progress report
- In the ERP
- Earned Value
Measure
Task 3 · 15 min
Actual cost is not what accounting booked
- You produce
- Actual cost with accruals
- Document
- Job cost report
- In the ERP
- Earned Value
Forecast
Task 4 · 20 min
The outturn, and whether the contingency covers it
- You produce
- Outturn and the GMP overrun
- Document
- Monthly report
- In the ERP
- Earned Value
Change
Task 5 · 20 min
Rev 2: what may move into the baseline
- You produce
- Baseline rev 2
- Document
- Change log
- In the ERP
- Earned Value
How one report answers 'is the GMP safe?'
Each step below is one task, in the order the report is built.
Blue is what the task adds; grey is carried over from before.
In short. Measure against authorized work, earn at budget, cost the same work, forecast from performance, and never re-budget the past.