Theory before task 1 · 8 min

The performance measurement baseline and what stays outside it

The budget the lender measures you against

Course introduction

After this lecture you can

  1. Say what the performance measurement baseline holds and what it does not.
  2. Separate cost of the work, approved changes, contingency and fee in a GMP.
  3. Work out the budget at completion from a GMP build-up.
1 / 3

A GMP is four layers

A guaranteed maximum price stacks the estimated cost of the work, the construction manager's contingency and the fee. Approved change orders add their own cost and fee on top. Earned value measures only the work: the layers that hold budget for defined work form the performance measurement baseline, and its total is the budget at completion (BAC).

Example. On a parking structure with $5,000,000 of work, $200,000 contingency and a $180,000 fee, the BAC is $5,000,000 until a change is approved.
$5,000,000
  • Cost of the work $5,000,000
  • Contingency $200,000
  • Fee $180,000
2 / 3

Contingency is management reserve

Reserve is money for work nobody has identified yet. It has no schedule and no scope, so nothing can be planned or earned against it. It joins the baseline only when it is moved to a control account for real, newly found work.

Example. If contingency sat in BAC, the percent complete would be understated from day one and the CPI would mean nothing.
Common mistake

Dividing by the GMP

The GMP is the number everyone knows, so it ends up in the BAC field. Fee and reserve then inflate the budget, and every percent complete and forecast built on it is wrong until the last month.

Example. Ask of each layer: is there defined, authorized work behind it? Only then is it baseline.

BAC from a GMP

Different numbers from your task.

Not to scale
The problem
  • Cost of the work $5,000,000; approved change $72,000; contingency $200,000.
  • A priced change of $41,000 waits for the owner's signature.
Step 1 of 1

Authorized work

What is the budget at completion?

$5,000,000 + $72,000 = $5,072,000.

In short. Authorized work only: the cost of the work plus approved changes.

Check yourself

Question 1 of 3

A change is priced and the owner's rep has said yes on the phone. Does it join the baseline?

  • Right. The baseline follows authorization, not expectation.

  • Track it on the change log until it is authorized.

  • A baseline never holds weighted values.

Question 2 of 3

Where does the CM fee sit?

  • Right. The fee pays for no work, so it earns nothing.

  • The fee is margin, not budget for work.

  • Contingency and fee are separate layers.

Question 3 of 3

Work $3,200,000, approved changes $45,000, contingency $96,000, fee $115,000. What is the BAC?

3,200,000 + 45,000 = 3,245,000.