A GMP is four layers
A guaranteed maximum price stacks the estimated cost of the work, the construction manager's contingency and the fee. Approved change orders add their own cost and fee on top. Earned value measures only the work: the layers that hold budget for defined work form the performance measurement baseline, and its total is the budget at completion (BAC).
- Cost of the work $5,000,000
- Contingency $200,000
- Fee $180,000