OpenConstruction Academy
Sign in / Register
EN

Theory before task 2 · 9 min

Earned value: progress priced at budget

What the October work was worth

After this lecture you can

  1. Say why earned value is a budget and not a cost.
  2. Earn a control account from its physical percent complete.
  3. Earn level of effort with time.
1 / 3

Three figures, one picture

Planned value (PV) is the budget of the work scheduled by the data date. Earned value (EV) is the budget of the work actually done. Actual cost (AC) is what that work cost. EV is compared with PV for schedule and with AC for cost, so EV must never be built from either.

Example. A $400,000 account planned at half done and found 40 % done has earned $160,000, whatever it cost.
Planned value
$200,000
Earned value
$160,000
2 / 3

Level of effort

Supervision, site offices and other general conditions have no product to measure. They earn with time: earned value equals planned value. That hides any schedule slip inside them, which is why level of effort is kept small and separate.

Example. General conditions of $600,000 over 12 months earn $50,000 a month, whatever happens on site.
Common mistake

Percent of the plan

Percent complete is a share of the whole account. Applied to planned value it shrinks earned value whenever the account is behind, and the schedule variance is counted twice.

Example. 40 % of a $400,000 account is $160,000; 40 % of its $200,000 plan would report only $80,000.

Earned value of three accounts

Different numbers from your task.

Not to scale
The problem
  • Account A budget $400,000, 40% complete; account B budget $900,000, 70% complete.
  • General conditions $600,000 over 12 months; month 5 has ended.
Step 1 of 2

Measured work

Earned value of A and B together?

160,000 + 630,000 = $790,000.

Step 2 of 2

Level of effort

Earned value of the job?

$790,000 + 250,000 = $1,040,000.

In short. Budget × % complete for measured work; time for level of effort.

Check yourself

Question 1 of 3

An account cost more than planned. Does that raise its earned value?

  • Right. That independence is what makes the CPI meaningful.

  • Then EV would always equal AC and the CPI would always be 1.

  • The rule is the same for every account.

Question 2 of 3

A change order has not started. What does it earn?

  • Right. Its budget waits in the baseline until work starts.

  • Progress on the base scope says nothing about new work.

  • Only level of effort earns its plan.

Question 3 of 3

Budget $250,000, 36 % complete. Earned value?

250,000 × 36 % = 90,000.

Read the source

Free official texts. The lecture cites clause numbers and puts the rules in its own words.