Theory before task 3 · 8 min

Actual cost: accruals, prepayments and commitments

Actual cost is not what accounting booked

After this lecture you can

  1. Say why actual cost must cover the same work as earned value.
  2. Accrue work done but not invoiced; take out prepayments.
  3. Keep open commitments out of actual cost.
1 / 3

Same work, same period

The CPI divides earned value by actual cost. If October's work is in earned value but its invoice comes in November, October's cost is too low and the CPI too good. Accruals put the cost of work performed into the period it was performed.

Example. A sub's approved October progress is October cost, even if the pay application arrives on 10 November.
+$1,200,0001−$40,0002+$85,0003$1,245,0004
  • 1 Booked
  • 2 Prepayment
  • 3 Accruals
  • 4 Actual cost
2 / 3

Paid is not performed

A deposit on equipment that has not arrived is money out, but no work exists for it yet. It is a prepayment until the equipment is received for the work. A commitment, a signed subcontract or purchase order, is cost still to come.

Example. A $40,000 deposit on a chiller due in three months stays out of actual cost until the chiller arrives.
Common mistake

Taking accounting's figure as it is

The job cost report is built for the books and the bank. It books invoices and payments when they happen. Without the accrual list it reports a CPI that looks fine until the invoices land.

Example. Agree the accrual list with accounting before the report goes out.

Correcting the booked cost

Different numbers from your task.

Not to scale
The problem
  • Booked $1,200,000, including a deposit of $40,000.
  • Work done, not invoiced: $60,000 and $25,000. Open commitments $900,000.
Step 1 of 1

Actual cost

What is actual cost?

$1,200,000 − $40,000 + $60,000 + $25,000 = $1,245,000.

In short. Booked − prepayments + accruals; commitments stay out.

Check yourself

Question 1 of 3

A signed PO for $300,000 of doors, nothing delivered. Actual cost?

  • Right. It becomes cost as doors arrive for the work.

  • Committed is not incurred.

  • Cost follows delivery and work, not averages.

Question 2 of 3

Missing accruals make the CPI...

  • Right. Less cost against the same earned value.

  • Less cost raises the CPI.

  • Actual cost is the CPI's divisor.

Question 3 of 3

Booked $800,000 with a $30,000 deposit inside; accruals $55,000. Actual cost?

800,000 − 30,000 + 55,000 = 825,000.