Theory before task 4 · 9 min

Forecasting the outturn and reading the TCPI

The outturn, and whether the contingency covers it

After this lecture you can

  1. Compute EAC by three standard formulas and say what each assumes.
  2. Use the TCPI to test a recovery claim.
  3. Say who pays an overrun under a GMP.
1 / 3

Three outturns, three assumptions

remaining: AC + (BAC − EV), the past overrun was a one-off. cpi: BAC ÷ CPI, the cost efficiency so far continues. combined: AC + (BAC − EV) ÷ (CPI × SPI), being late keeps costing money. They disagree by design; a report names the method it headlines and shows the range.

Example. With BAC $2,000,000, EV $800,000 and AC $880,000, the cpi method forecasts $2,200,000.
BAC$2,000,000
CPI = EV ÷ AC0.91
EAC by cpi = BAC ÷ CPI$2,200,000
2 / 3

TCPI: the efficiency still needed

TCPI = (BAC − EV) ÷ (BAC − AC): the value each remaining dollar must earn to finish on budget. When it sits well above the CPI achieved so far, finishing on budget needs a change on site, not hope.

Example. CPI 0.91 and TCPI 1.08: each remaining dollar must earn 19 % more than the dollars so far.
Common mistake

Forgetting the contingency layer

Under a GMP an overrun of the cost of the work is paid from the contingency first. Only the part beyond it is the construction manager's own money. The fee is fixed and absorbs nothing.

Example. VAC of −$300,000 with $200,000 contingency leaves $100,000 for the CM.

Outturn and exposure

Different numbers from your task.

Not to scale
The problem
  • BAC $2,000,000, EV $800,000, AC $880,000.
  • Contingency $120,000, nothing drawn.
Step 1 of 2

Outturn

EAC by the cpi method?

$2,000,000 × $880,000 ÷ $800,000 = $2,200,000.

Step 2 of 2

Exposure

What does the CM pay beyond contingency?

$2,200,000 − $2,000,000 − $120,000 = $80,000.

In short. EAC by the agreed method; contingency first, then the CM.

Check yourself

Question 1 of 3

SPI is 0.80 and the owner insists on the original finish date. Which EAC is the honest upper end?

  • Right. CPI × SPI lets the schedule pressure drive the forecast.

  • That assumes the rest runs on budget, the most optimistic case.

  • cpi ignores the schedule; it is the middle case here.

Question 2 of 3

TCPI 1.15 against a CPI of 0.95 means...

  • Right.

  • TCPI is needed efficiency, not achieved.

  • It argues for raising it.

Question 3 of 3

BAC $1,000,000, EV $400,000, AC $500,000. EAC by cpi?

1,000,000 ÷ 0.8 = 1,250,000.