Three sources of money
An owner-approved change brings its own money and raises the GMP. Work that was always in the contract but never budgeted is funded by moving contingency into a control account. An overrun on work already done gets no new budget: it stays a variance and is reported.
- Rev 1 $2,000,000
- Owner change $60,000
- From contingency $25,000