Theory before task 5 · 8 min

Changing the baseline without hiding a variance

Rev 2: what may move into the baseline

After this lecture you can

  1. Say which changes may enter the baseline and where their money comes from.
  2. Fund newly found in-scope work from contingency.
  3. Refuse a transfer that would cover an overrun.
1 / 3

Three sources of money

An owner-approved change brings its own money and raises the GMP. Work that was always in the contract but never budgeted is funded by moving contingency into a control account. An overrun on work already done gets no new budget: it stays a variance and is reported.

Example. A missed fire damper schedule found in month 9 is moved from contingency into the mechanical account.
$2,000,000
  • Rev 1 $2,000,000
  • Owner change $60,000
  • From contingency $25,000
2 / 3

Future, not past

A legitimate change adds budget for work still to do. Earned value and actual cost to date do not move, so the CPI to date does not move either. If a change improves the CPI to date, it changed the past.

Example. Rev 2 adds $85,000 of work to come; the CPI to date is the same on both revisions.
Common mistake

Moving contingency to clean up an account

Moving reserve into an account that has overrun makes its budget match its cost and the variance disappears. The money is still spent; only the warning is gone, and the lender loses the signal it pays for.

Example. Report the overrun; draw contingency only for new work.

Rev 2 and the contingency

Different numbers from your task.

Not to scale
The problem
  • Rev 1 BAC $2,000,000; owner-approved change $60,000; missed in-scope work $25,000.
  • Contingency $150,000; a request to move $40,000 to an overrunning account.
Step 1 of 2

Rev 2

Rev 2 budget at completion?

$2,000,000 + $60,000 + $25,000 = $2,085,000.

Step 2 of 2

Contingency

Contingency left?

$150,000 − $25,000 = $125,000.

In short. The owner pays changes, contingency pays missed scope, nobody re-budgets an overrun.

Check yourself

Question 1 of 3

Who funds an owner-approved change order?

  • Right.

  • Contingency is for the CM's own risks.

  • The fee is fixed margin.

Question 2 of 3

After rev 2 the CPI to date rose. What happened?

  • Right. Check the transfers.

  • New work has not started.

  • The data to date did not change.

Question 3 of 3

Contingency $300,000; missed in-scope work $45,000; owner change $80,000. Contingency left?

300,000 − 45,000 = 255,000.