Course introduction · 3 min
Road earthworks: cut, fill, haul and rate (Saudi Arabia)
You are the quantity surveyor at the design consultant for a municipality's new link road. The tender goes out on Sunday. In five tasks you measure the cut, the topsoil and the borrow, price the long haul, and build the rate for digging in a Saudi summer.
Fictional project- Works
- 1.2 km two-lane road: earthworks, pavement, culverts
- Contract
- Municipal tender, unit-rate BOQ, engineer's estimate in SAR
- Method
- Average end areas, PDF takeoff, swell and shrinkage, mass haul, cost-based rate
- Work in the ERP
- 5 tasks, about 1 h 20 min
Who hands what to whom
Every arrow is a figure that reaches your desk or leaves it, and the task where that happens.
Comes to you
- DesignerCross sections and plan
- SectionsTask 1
- Plan C-101Task 2
- Geotechnical engineerSoils report
- FactorsTask 3
YouQuantity surveyor, design consultantGoes from you
- Tender BOQTask 1
- OverhaulTask 4
- RateTask 5
The project and the people are fictional. Portraits are generated.
Your route through the job
One bill, from blank lines to the engineer's estimate. Every task is free.
Measure
Task 1 · 10 min
Cut 1 by average end areas
- You produce
- Cut volume
- Document
- Tender BOQ
- In the ERP
- Bill of Quantities
Measure
Task 2 · 20 min
Topsoil off the plan
- You produce
- Topsoil strip
- Document
- Tender BOQ
- In the ERP
- PDF Takeoff
Balance
Task 3 · 15 min
How much borrow?
- You produce
- Borrow
- Document
- Tender BOQ
- In the ERP
- Bill of Quantities
Balance
Task 4 · 15 min
Overhaul off the mass haul diagram
- You produce
- Overhaul
- Document
- Tender BOQ
- In the ERP
- Bill of Quantities
Price
Task 5 · 20 min
A rate for roadway excavation
- You produce
- Excavation rate
- Document
- Engineer's estimate
- In the ERP
- Bill of Quantities
How the ground becomes a bill
Each step below is one task, in the order the tender needs it.
Blue is what the task adds; grey is carried over from before.
In short. Measure the soil once, in place, and let every factor and every truck live in the rate.