Course introduction · 3 min

Road earthworks: cut, fill, haul and rate (Saudi Arabia)

You are the quantity surveyor at the design consultant for a municipality's new link road. The tender goes out on Sunday. In five tasks you measure the cut, the topsoil and the borrow, price the long haul, and build the rate for digging in a Saudi summer.

Start task 1

A desert road corridor in central Saudi Arabia, survey pegs along a low ridge and a dry wadi beyond, before earthworks start.Fictional project
Wadi Saffan link roadA new road across a low ridge and a wadi
Works
1.2 km two-lane road: earthworks, pavement, culverts
Contract
Municipal tender, unit-rate BOQ, engineer's estimate in SAR
Method
Average end areas, PDF takeoff, swell and shrinkage, mass haul, cost-based rate
Work in the ERP
5 tasks, about 1 h 20 min

Who hands what to whom

Every arrow is a figure that reaches your desk or leaves it, and the task where that happens.

Comes to you

  • DesignerCross sections and plan
    • SectionsTask 1
    • Plan C-101Task 2
  • Geotechnical engineerSoils report
    • FactorsTask 3
YouQuantity surveyor, design consultant

Goes from you

    • Tender BOQTask 1
    • OverhaulTask 4
    BiddersRoad contractors
    • RateTask 5
    MunicipalityApproves the estimate

The project and the people are fictional. Portraits are generated.

Your route through the job

One bill, from blank lines to the engineer's estimate. Every task is free.

  1. Measure

    Task 1 · 10 min

    Cut 1 by average end areas

    You produce
    Cut volume
    Document
    Tender BOQ
    In the ERP
    Bill of Quantities
  2. Measure

    Task 2 · 20 min

    Topsoil off the plan

    You produce
    Topsoil strip
    Document
    Tender BOQ
    In the ERP
    PDF Takeoff
  3. Balance

    Task 3 · 15 min

    How much borrow?

    You produce
    Borrow
    Document
    Tender BOQ
    In the ERP
    Bill of Quantities
  4. Balance

    Task 4 · 15 min

    Overhaul off the mass haul diagram

    You produce
    Overhaul
    Document
    Tender BOQ
    In the ERP
    Bill of Quantities
  5. Price

    Task 5 · 20 min

    A rate for roadway excavation

    You produce
    Excavation rate
    Document
    Engineer's estimate
    In the ERP
    Bill of Quantities

How the ground becomes a bill

Each step below is one task, in the order the tender needs it.

Cut
Task 1In placeEnd areas × interval.
Topsoil
Task 2Off the planArea × depth.
Borrow
Task 3BalanceFill needed − cut × 0.88.
Overhaul
Task 4HaulBeyond the free haul.
O&PCost
Task 5RateDay cost ÷ day output.

Blue is what the task adds; grey is carried over from before.

In short. Measure the soil once, in place, and let every factor and every truck live in the rate.