Theory before task 1 · 6 min

Cut volume by average end areas

Cut 1 by average end areas

Course introduction

After this lecture you can

  1. Read a cut as slices between cross sections.
  2. Compute a slice by the mean of its two end areas.
  3. Keep swell and compaction out of the measured volume.
1 / 3

A road cut is a stack of slices

The designer draws a cross section every 20 or 25 m along the road and measures the area of cut on each. Between two sections the ground changes smoothly, so a slice is taken as a prism whose area is the mean of its two ends. The volume of the cut is the sum of its slices.

Example. Sections of 10 and 30 m2, 20 m apart: (10 + 30) ÷ 2 × 20 = 400 m3.
Section A
SAR10
Mean of the slice
SAR20
Section B
SAR30
2 / 3

Ends count half

Adding all the slices, every inner section appears twice and is halved twice, so it counts once; the first and last sections count only half. Where a cut starts and ends at zero, the volume is the interval times the sum of the inner areas.

Example. Five sections 0, 12, 20, 8, 0 m2 at 20 m: 20 × (12 + 20 + 8) = 800 m3.
Inner sections, 12 + 20 + 8, m240.00 m²
End sections, 0 each, half weight0.00 m²
Volume at 20 m intervals, m3800.00 m²
Common mistake

Measuring the soil in the truck

Dug soil swells: a cubic metre in the ground fills about 1.2 to 1.3 m3 of a truck body. The bill measures the cut once, in its original position. Swell is the bidder's own allowance and goes in the rate.

Example. 600 m3 in place is still 600 m3 in the bill, though it leaves in about 750 m3 of trucks.

Volume of another cut

Different numbers from your task.

Not to scale
The problem
  • Sections at 20 m intervals: 0, 12.00 m², 20.00 m², 8.00 m², 0 m2.
Step 1 of 2

Inner sections

Sum of the three inner areas, m2?

12.00 m² + 20.00 m² + 8.00 m² = 40.00 m².

Step 2 of 2

Volume

Volume of the cut, m3?

40.00 m² × 20.0 m = 800.00 m² m3, in place.

In short. Mean of each pair of end areas × the interval, summed; the volume stays in place.

Check yourself

Question 1 of 3

Two sections of 40 and 60 m2 are 25 m apart. Volume of the slice?

  • Right. 50 × 25.

  • That adds both areas without averaging.

  • That uses the larger area only.

Question 2 of 3

Where does the cost of swell go in a bill measured in place?

  • Right.

  • The quantity stays in place.

  • Not in this bill.

Question 3 of 3

Sections 0, 15, 25, 0 m2 at 20 m intervals. Volume, m3?

(15 + 25) × 20 = 800 m3.

Read the source