Road earthworks: cut, fill, haul and rate (Saudi Arabia)

On an invented link road for a Saudi municipality.

Who it's for Quantity surveyor at the design consultant (road earthworks)

Workspace: Road earthworks: cut, fill, haul and rate (Saudi Arabia)
Cut 1 by average end areas

You will be able to

Skills checked

  • Work the cut volume from cross sections by average end areas, in place and not loose
  • Measure a topsoil strip on a plan in PDF Takeoff: calibrate, outline the strip and apply the depth
  • Find the borrow an embankment needs, with the cut converted by the shrinkage factor
  • Price overhaul beyond the free haul from the centres of gravity of a mass haul diagram
  • Build an excavation rate from the fleet, with the summer working hours and overheads

Tasks

A task as it opens in the trainer, before you enter anything.

Task 1 as it opens in the trainer: Cut 1 by average end areas
  1. 1
    Cut 1 by average end areasFoundation≈10 minTheory · 6 min
  2. 2
    Topsoil off the planFoundation≈20 minPDF takeoffTheory · 6 min
  3. 3
    How much borrow?Foundation≈15 minTheory · 7 min
  4. 4
    Overhaul off the mass haul diagramFoundation≈15 minTheory · 6 min
  5. 5
    A rate for roadway excavationFoundation≈20 minTheory · 7 minCheat sheet: every rule on one page

Difficulty is calculated from the steps and the figures you check in each task. Time is the median of real learners once enough have finished; until then it is the author's estimate.

Videos on this method

Certificate

Awarded when all 5 tasks pass the numbers, trace and explain checks.

Certificates

Sample: Certificate of completion
Sample issued to a fictitious learner. Your certificate shows your name, the course, the date and its own ID.
Check this sample

Files you work with

Created in your OpenConstructionERP workspace the moment you enrol.

  • Estimatebill of quantities15 lines
  • Documentsdrawings and model1 file
  • parties3 records

Start free course All courses

What next

Next in the learning pathClaims and extension of time (Saudi Arabia, FIDIC)Advanced · 2 h of study

When you pass, add the certificate to LinkedIn from your account. Anyone can open its verification link, no sign-in needed. How to add it

Questions about this course? Write to info@datadrivenconstruction.io

Related courses

Start free: task 1 of 5All 5 tasks free · 1.5 h of study

Start free course