Theory before task 3 · 7 min

Cut, fill and borrow: swell and shrinkage

How much borrow?

After this lecture you can

  1. Tell in-place, loose and compacted volumes apart.
  2. Balance fill needed against fill the cut supplies.
  3. State borrow in the unit the bill measures it.
1 / 3

One soil, three volumes

A cubic metre in the ground swells when dug, to perhaps 1.25 m3 in the truck, and shrinks below where it started when rolled into an embankment, to perhaps 0.85 to 0.9 m3. Each line of the bill names the state it measures. Cut is in place; embankment and borrow, here, compacted.

Example. 100 m3 in place: 125 m3 loose, 88 m3 compacted with this job's factors.
In place
SAR100
Loose
SAR125
Compacted
SAR88
2 / 3

The balance

Fill needed is every line that takes fill: the embankment and any backfill of material removed. Fill supplied is the suitable cut, converted to compacted. Borrow is the gap, brought in from a pit and measured compacted in place.

Example. Needed 10,000 m3; cut 8,000 m3 × 0.88 = 7,040 m3; borrow 2,960 m3.
+SAR10,0001−SAR7,0402SAR2,9603
  • 1 Fill needed
  • 2 Cut, compacted
  • 3 Borrow
Common mistake

The swell factor on the way to the fill

The swell factor is the bigger, more familiar number, so it is the one people reach for. It describes the truck, not the embankment: using it makes the cut look larger than it is and the borrow too small.

Example. Use the factor that names the state you are converting to.

Borrow for another job

Different numbers from your task.

Not to scale
The problem
  • Embankment 12,000.00 m² m3 and backfill 1,500.00 m² m3, compacted; cut 9,000.00 m² m3 in place; 1 m3 in place makes 0.88 m3 compacted.
Step 1 of 2

Cut as fill

Cut, compacted m3?

9,000.00 m² × 0.88 = 7,920.00 m².

Step 2 of 2

Borrow

Borrow, compacted m3?

12,000.00 m² + 1,500.00 m² − 7,920.00 m² = 5,580.00 m².

In short. Needed (all fill lines) − cut × shrinkage factor; borrow in compacted m3.

Check yourself

Question 1 of 2

1 m3 in place makes 0.9 m3 compacted. 1,000 m3 of cut builds how much embankment?

  • Right.

  • That divides by 0.9.

  • That is the loose volume.

Question 2 of 2

Sabkha removed under an embankment is replaced. Where does its backfill come from?

  • Right: it adds to the fill needed.

  • Sabkha goes to spoil.

  • The hole must be filled.

Read the source