Theory before task 4 · 6 min

Mass haul and overhaul

Overhaul off the mass haul diagram

After this lecture you can

  1. Read a mass haul diagram for where cut goes.
  2. Measure haul between centres of gravity.
  3. Pay overhaul only beyond the free haul.
1 / 3

The mass haul diagram

Walk along the road adding cut and subtracting fill, all in the same state, and plot the running total. The curve rises through cuts and falls through fills; where it crosses a horizontal line, cut and fill balance between the two crossings. The diagram shows which cut feeds which fill, and how far it travels.

Example. A curve rising 9,000 m3 over a cut and falling back over the next fill: that cut builds that fill.
After the cut
SAR9,000
Halfway through the fill
SAR4,500
End of the fill
SAR0
2 / 3

Free haul and overhaul

Every load of cut travels a different distance; the average is the distance between the centre of gravity of the cut and that of the fill. The excavation rate includes a free haul. Beyond it, the bill pays overhaul: volume in place times the extra distance.

Example. 6,000 m3 hauled 800 m with 400 m free: 6,000 × 0.4 km = 2,400 m3.km.
SAR400SAR400
  • Free haul, in the excavation rate SAR400
  • Overhaul, its own line SAR400
Common mistake

The longest trip

Measuring from the start of the cut to the far end of the fill pays every load as if it went the whole way. The first load to leave a cut usually goes to the nearest end of the fill; the average trip is centre to centre.

Example. Read centres of gravity, not ends.

Overhaul on another job

Different numbers from your task.

Not to scale
The problem
  • 6,000.00 m² m3 in place; centres of gravity 800.0 m m apart; free haul 400 m.
Step 1 of 2

Overhaul distance

Distance beyond free haul, km?

(800.0 m − free haul) ÷ 1,000 = 0.4 m.

Step 2 of 2

Overhaul

Overhaul, m3.km?

6,000.00 m² × 0.4 m = 2,400.00 m².

In short. Volume in place × (centre-to-centre haul − free haul), in m3.km.

Check yourself

Question 1 of 2

Haul 450 m, free haul 400 m. Overhaul?

  • Right: within free haul.

  • Distance cannot be negative overhaul.

  • All of it is free.

Question 2 of 2

Which volume does overhaul use in this bill?

  • Right.

  • Not measured.

  • Not for overhaul.