Two machines in series
The excavator loads, the trucks carry. Whichever moves less per hour sets the pace; the other waits. Put both in the same unit: the excavator's output is quoted in place, a truck body is loose, so divide the body by the swell.
Theory before task 5 · 7 min
A rate for roadway excavation
The excavator loads, the trucks carry. Whichever moves less per hour sets the pace; the other waits. Put both in the same unit: the excavator's output is quoted in place, a truck body is loose, so divide the body by the swell.
Plant is hired by the day. The rate is the day's cost divided by what the fleet actually digs that day, plus overheads and profit. In Saudi summers outdoor work stops from 12:00 to 15:00 between 15 June and 15 September, so a paid day digs for fewer hours.
Dividing by the excavator's output prices a fleet that never waits. If the trucks are the bottleneck, the rate is too low by the gap between them, on every cubic metre of the job.
Different numbers from your task.
m3 a day?
Hint: Output × hours dug.
Rate, SAR per m3?
Hint: Cost ÷ output, then + 10 %.
Right: the trucks govern.
The excavator waits for trucks.
They work in series.
Right: 10 ÷ 7 = 1.43.
That is the share of hours lost, not the rise in cost per m3.
The day costs the same and digs less.
Free official texts. The lecture cites clause numbers and puts the rules in its own words.
When an engineer's estimate builds a unit price from crews, equipment and production rather than past bids.
Swell factors again: the truck carries loose soil, the rate is per m3 in place.