Theory before task 5 · 7 min

A cost-based rate for excavation

A rate for roadway excavation

After this lecture you can

  1. Find the output of a load-and-haul fleet.
  2. Turn a day's cost into a rate per m3 in place.
  3. Allow for the hours the summer ban takes out.
1 / 3

Two machines in series

The excavator loads, the trucks carry. Whichever moves less per hour sets the pace; the other waits. Put both in the same unit: the excavator's output is quoted in place, a truck body is loose, so divide the body by the swell.

Example. 3 trucks, 18 m3 loose, 30-minute trips, swell 1.2: 3 × 2 × 15 = 90 m3 in place an hour.
Excavator
SAR120
Trucks
SAR90
2 / 3

From a day to a cubic metre

Plant is hired by the day. The rate is the day's cost divided by what the fleet actually digs that day, plus overheads and profit. In Saudi summers outdoor work stops from 12:00 to 15:00 between 15 June and 15 September, so a paid day digs for fewer hours.

Example. SAR 6,000 a day, 90 m3 an hour, 8 hours: 6,000 ÷ 720 = SAR 8.33 per m3 before overheads.
+SAR8.331+SAR12SAR9.333
  • 1 Cost per m3
  • 2 Overheads and profit
  • 3 Rate
Common mistake

The machine's brochure

Dividing by the excavator's output prices a fleet that never waits. If the trucks are the bottleneck, the rate is too low by the gap between them, on every cubic metre of the job.

Example. Price what the slower machine delivers.

Rate for another fleet

Different numbers from your task.

Not to scale
The problem
  • Day cost SAR SAR6,000; output 90.00 m² m3 in place an hour; 8.0 m hours dug; 10 % overheads and profit.
Step 1 of 2

Daily output

m3 a day?

90.00 m² × 8.0 m = 720.00 m².

Step 2 of 2

Rate

Rate, SAR per m3?

SAR6,000 ÷ 720.00 m² × 1.10 = SAR9.17.

In short. Day cost ÷ (governing output × hours dug) × (1 + overheads and profit).

Check yourself

Question 1 of 2

Excavator 150 m3/h; trucks 120 m3/h, both in place. Fleet output?

  • Right: the trucks govern.

  • The excavator waits for trucks.

  • They work in series.

Question 2 of 2

A 10-hour paid day loses 3 hours to the midday ban. The rate rises by about...

  • Right: 10 ÷ 7 = 1.43.

  • That is the share of hours lost, not the rise in cost per m3.

  • The day costs the same and digs less.

Read the source

Free official texts. The lecture cites clause numbers and puts the rules in its own words.