Cheat sheet
Road earthworks: cut, fill, haul and rate (Saudi Arabia)
Every rule of the course on one page: how each figure is built, the mistake people usually make, and where it comes up at work. Print it or keep it open while you work.
- Rule
- Measure the cut in place. Mean of each pair of end areas × 25 m, summed; swell stays in the rate.
- How it is built
- Cut 1 volume = 25 m × Sum of inner areas
- Usual mistake
- That is the loose volume, with 25 % swell. Line 1.3 is measured in its original position; the swell goes in the rate.
- At work
- The consultant's QS takes cut and fill off the designer's cross sections before the tender BOQ goes out.
- Rule
- The whole footprint, in place. Area inside the stripping limit × 0.15 m; depth in metres.
- How it is built
- Topsoil strip = Volume inside the stripping limit, group TS
- Usual mistake
- You measured the road's 10.30 m width. The strip runs to the stripping limit, past the slopes.
- At work
- On road jobs the earthworks limits are taken off the plan in the takeoff tool and checked against the offsets.
- Rule
- Compare like with like. Fill needed (1.6 + 1.7) less all cut × 0.88; borrow is compacted in place.
- How it is built
- Borrow = Fill needed − Cut × 0.88
- Usual mistake
- You used the 1.25 swell. That is the loose volume in the truck; compacted fill is less than in place: 0.88.
- At work
- The earthworks balance is checked against the soils report before the borrow and spoil lines are fixed.
- Rule
- Pay only the extra distance. Volume in place × (centre-to-centre haul − 500 m), in km.
- How it is built
- Overhaul = Cut 1 × Haul beyond 500 m, km
- Usual mistake
- The free haul is still in. The first 500 m are paid in the excavation rate: take them off.
- At work
- The mass haul diagram comes from the designer's earthworks software; the QS turns it into the overhaul line.
- Rule
- Price what the slower machine digs in the hours allowed. Day cost ÷ (governing output × 7 h) × 1.12.
- How it is built
- Rate = Unit Rate of 1.3
- Usual mistake
- You counted 10 working hours. From 12:00 to 15:00 nobody digs in summer: 7 hours.
- At work
- For major earthworks the engineer's estimate is built from the fleet's cost and output, not from old bids alone.