Road earthworks: cut, fill, haul and rate (Saudi Arabia)

Every rule of the course on one page: how each figure is built, the mistake people usually make, and where it comes up at work. Print it or keep it open while you work.

Task 1

Cut 1 by average end areas

Theory (6 min)
Rule
Measure the cut in place. Mean of each pair of end areas × 25 m, summed; swell stays in the rate.
How it is built
  • Cut 1 volume = 25 m × Sum of inner areas
Usual mistake
That is the loose volume, with 25 % swell. Line 1.3 is measured in its original position; the swell goes in the rate.
At work
The consultant's QS takes cut and fill off the designer's cross sections before the tender BOQ goes out.

Task 2

Topsoil off the plan

Theory (6 min)
Rule
The whole footprint, in place. Area inside the stripping limit × 0.15 m; depth in metres.
How it is built
  • Topsoil strip = Volume inside the stripping limit, group TS
Usual mistake
You measured the road's 10.30 m width. The strip runs to the stripping limit, past the slopes.
At work
On road jobs the earthworks limits are taken off the plan in the takeoff tool and checked against the offsets.

Task 3

How much borrow?

Theory (7 min)
Rule
Compare like with like. Fill needed (1.6 + 1.7) less all cut × 0.88; borrow is compacted in place.
How it is built
  • Borrow = Fill needed − Cut × 0.88
Usual mistake
You used the 1.25 swell. That is the loose volume in the truck; compacted fill is less than in place: 0.88.
At work
The earthworks balance is checked against the soils report before the borrow and spoil lines are fixed.

Task 4

Overhaul off the mass haul diagram

Theory (6 min)
Rule
Pay only the extra distance. Volume in place × (centre-to-centre haul − 500 m), in km.
How it is built
  • Overhaul = Cut 1 × Haul beyond 500 m, km
Usual mistake
The free haul is still in. The first 500 m are paid in the excavation rate: take them off.
At work
The mass haul diagram comes from the designer's earthworks software; the QS turns it into the overhaul line.

Task 5

A rate for roadway excavation

Theory (7 min)
Rule
Price what the slower machine digs in the hours allowed. Day cost ÷ (governing output × 7 h) × 1.12.
How it is built
  • Rate = Unit Rate of 1.3
Usual mistake
You counted 10 working hours. From 12:00 to 15:00 nobody digs in summer: 7 hours.
At work
For major earthworks the engineer's estimate is built from the fleet's cost and output, not from old bids alone.