Course introduction · 3 min

Tender estimate: from net rates to the tender sum

Mixed-use building, 6 storeys · Tender due Thursday 12:00 · Fictional project

You are the main contractor's estimator. The bill of quantities for a six-storey mixed-use building is measured, and the tender is due on Thursday at 12:00. In five tasks you take it from quantities to the one figure the company signs: net rates, preliminaries, provisional sums, and the mark-ups added once.

Start task 1

Building
Shops on the ground floor, offices on level 1, flats on levels 2 to 5; concrete frame
Stage
Tender: the bill is measured, the price is not
Contract
FIDIC Red Book 2017, remeasured; US dollars; taxes left out
Work in the ERP
5 tasks, about 1 h 12 min

Who hands what to whom

Every arrow is a figure that reaches your desk or leaves it, and the task where that happens.

Comes to you

  • Facade subcontractorQuotes the cladding
    • QuoteTask 1
  • MEP subcontractorOffers the services
    • Lower offerTask 4
YouEstimator

Goes from you

    • Tender sumTask 5
    The clientReceives the tender
    • Provisional sumsTask 4
    The EngineerInstructs provisional sums

Your route through the job

One tender estimate, in the order an estimator closes it. All tasks are free; each happens in the Bill of Quantities.

  1. Net rates

    Task 1 · 10 min

    A subcontract quote goes into the bill as a net rate

    You produce
    Envelope section total
    Document
    Tender estimate
    In the ERP
    Bill of Quantities
  2. Net rates

    Task 2 · 15 min

    Rates stay net: take the mark-ups out of an all-in rate

    You produce
    Net rates for the measured work
    Document
    Tender estimate
    In the ERP
    Bill of Quantities
  3. Net cost

    Task 3 · 15 min

    Preliminaries: what the site costs for as long as it runs

    You produce
    Preliminaries
    Document
    Tender estimate
    In the ERP
    Bill of Quantities
  4. Net cost

    Task 4 · 12 min

    Provisional sums go in as stated

    You produce
    Net cost
    Document
    Tender estimate
    In the ERP
    Bill of Quantities
  5. Tender

    Task 5 · 20 min

    Mark-ups added once: the tender sum

    You produce
    Tender sum
    Document
    Letter of Tender
    In the ERP
    Bill of Quantities

How a bill of quantities becomes a tender sum

Each step below is one task, in the order the estimate is built.

Envelope
Task 1QuotesIn as they stand.
Measured
Task 2Net ratesAll-in back to net.
SiteMeasured
Task 3SiteFixed plus every month.
Net cost
Task 4SumsThe client's figures, as stated.
MarginNet cost
Task 5Mark-upsOnce, on the running total.

Blue is what the task adds; grey is carried over from before.

In short. Keep every rate net, put the site and the client's sums in at cost, and add the margin once.