Course introduction · 3 min
Tender estimate: from net rates to the tender sum
Mixed-use building, 6 storeys · Tender due Thursday 12:00 · Fictional project
You are the main contractor's estimator. The bill of quantities for a six-storey mixed-use building is measured, and the tender is due on Thursday at 12:00. In five tasks you take it from quantities to the one figure the company signs: net rates, preliminaries, provisional sums, and the mark-ups added once.
- Building
- Shops on the ground floor, offices on level 1, flats on levels 2 to 5; concrete frame
- Stage
- Tender: the bill is measured, the price is not
- Contract
- FIDIC Red Book 2017, remeasured; US dollars; taxes left out
- Work in the ERP
- 5 tasks, about 1 h 12 min
Who hands what to whom
Every arrow is a figure that reaches your desk or leaves it, and the task where that happens.
Comes to you
- Facade subcontractorQuotes the cladding
- QuoteTask 1
- MEP subcontractorOffers the services
- Lower offerTask 4
Goes from you
- Tender sumTask 5
- Provisional sumsTask 4
Your route through the job
One tender estimate, in the order an estimator closes it. All tasks are free; each happens in the Bill of Quantities.
Net rates
Task 1 · 10 min
A subcontract quote goes into the bill as a net rate
- You produce
- Envelope section total
- Document
- Tender estimate
- In the ERP
- Bill of Quantities
Net rates
Task 2 · 15 min
Rates stay net: take the mark-ups out of an all-in rate
- You produce
- Net rates for the measured work
- Document
- Tender estimate
- In the ERP
- Bill of Quantities
Net cost
Task 3 · 15 min
Preliminaries: what the site costs for as long as it runs
- You produce
- Preliminaries
- Document
- Tender estimate
- In the ERP
- Bill of Quantities
Net cost
Task 4 · 12 min
Provisional sums go in as stated
- You produce
- Net cost
- Document
- Tender estimate
- In the ERP
- Bill of Quantities
Tender
Task 5 · 20 min
Mark-ups added once: the tender sum
- You produce
- Tender sum
- Document
- Letter of Tender
- In the ERP
- Bill of Quantities
How a bill of quantities becomes a tender sum
Each step below is one task, in the order the estimate is built.
Blue is what the task adds; grey is carried over from before.
In short. Keep every rate net, put the site and the client's sums in at cost, and add the margin once.