Theory before task 1 · 6 min

A quote is a net rate

A subcontract quote goes into the bill as a net rate

Course introduction

After this lecture you can

  1. Say why a subcontract quote enters the bill as it stands.
  2. Check that a quote covers the bill item it prices.
  3. Work out a section total from quantities and rates.
1 / 3

The bill is built at cost

While the estimate is built, every rate in the bill is a net rate: what the work costs the main contractor. A subcontractor's quote already holds the subcontractor's own overheads and profit, so to the main contractor it is simply a cost. The company's own overheads, risk and profit are added once, on the whole net cost, at the end.

Example. A cladding quote of 380.00 per m2 on 1,200 m2 makes a net line of 456,000.00.
USD456,000
  • Cladding, net USD456,000
  • Roof, net USD30,000
2 / 3

Read the quote against the item

Before a quote goes in, compare its scope with the bill description: here insulation and the steel frame are part of the item. A quote that leaves something out needs the missing part priced, not a higher guess.

Example. A rainscreen quote without the support frame is not a price for the bill item.
Common mistake

A margin inside the rate

Typing the quote plus a percentage feels prudent. Then the summary adds the mark-ups again, and the client sees the margin twice. On a large line that alone can lose the tender.

Example. 456,000.00 with 13 % in the rate and 13 % again on the summary is about 582,000.00, not 515,000.00.

Section total of a smaller block

Different numbers from your task.

Not to scale
The problem
  • Cladding 1,200 m2 at a quoted USD380.00 per m2.
  • Roof 600 m2 at a quoted USD50.00 per m2.
Step 1 of 1

Section total

What is the section total, net?

1,200 x USD380.00 + 600 x USD50.00 = USD486,000.00.

In short. Quotes in as they stand; the section total is the sum of its lines.

Check yourself

Question 1 of 3

A subcontractor's quote includes its own overheads and profit. In your bill it is:

  • Right. Their margin is your cost.

  • Their margin is a real cost to you.

  • There is no split: it is what you pay.

Question 2 of 3

Where do the main contractor's own mark-ups go?

  • Right.

  • Then they come again at the end.

  • Every line carries the company's cost.

Question 3 of 3

800 m2 at 290.00 and 400 m2 at 45.00. Section total?

232,000 + 18,000 = 250,000.