Theory before task 2 · 7 min

Net and all-in rates

Rates stay net: take the mark-ups out of an all-in rate

After this lecture you can

  1. Tell a net rate from an all-in rate.
  2. Take compounded mark-ups out of a rate.
  3. Explain why the bill stays net until the summary.
1 / 3

Two kinds of rate

A net rate is labour, material, plant and subcontract cost. An all-in rate also carries the overheads, risk and profit of the tender it came from. Cost databases hold both, and the label is easy to lose.

Example. A rate from a past tender that won at a 10 % margin is 10 % above its net rate.
USD50
  • Net rate USD50
  • Overheads USD3
  • Risk USD1.06
  • Profit USD2.70
2 / 3

Compounded mark-ups come off by division

If each mark-up sat on the running total, the all-in rate is the net rate times every factor. So the net rate is the all-in rate divided by every factor. Subtracting the added percentages takes off too much.

Example. All-in 56.76 with 6 %, 2 % and 5 % on the running total: 56.76 / 1.06 / 1.02 / 1.05 = 50.00.
Common mistake

Subtracting the percentages

Taking 13 % off 56.76 gives 49.38, not 50.00. The percentages were charged on smaller bases than the all-in rate, so they cannot be taken off the all-in rate.

Example. Divide, one factor at a time, and round once at the end.

Back to net

Different numbers from your task.

Not to scale
The problem
  • All-in rate USD56.76 per m2.
  • Mark-ups on the running total: factors 1.06, 1.02 and 1.05.
Step 1 of 1

Net rate

What is the net rate?

USD56.76 / (1.06 x 1.02 x 1.05) = USD50.00.

In short. All-in / product of the factors = net.

Check yourself

Question 1 of 3

A rate in the database says 'all-in'. Before it goes in the bill you:

  • Right.

  • Its margin would be charged twice.

  • That takes off too much.

Question 2 of 3

Why round only at the end?

  • Right.

  • It takes cents.

  • It is arithmetic, not a clause.

Question 3 of 3

All-in 115.50 with one mark-up of 5 %. Net rate?

115.50 / 1.05 = 110.00.