Theory before task 3 · 7 min

Preliminaries: the cost of running the site

Preliminaries: what the site costs for as long as it runs

After this lecture you can

  1. Split preliminaries into fixed and time-related parts.
  2. Read the period from the Time for Completion.
  3. Price time-related items per month.
1 / 3

What preliminaries are

Preliminaries, also called site overheads or general requirements, are the costs of the site rather than of any one item of work: management, welfare, cranes, hoarding, temporary power. Some are paid once (set-up, removal); most are paid every month the site runs.

Example. A site with 20,000 per month of running costs over 14 months and 60,000 of set-up costs 340,000.
USD60,000USD280,000
  • Fixed USD60,000
  • Time-related USD280,000
2 / 3

The period comes from the contract

Under FIDIC the Time for Completion runs from the Commencement Date. The site runs at least that long, so the estimator prices the time-related part over that period, converted to the unit the cost is quoted in.

Example. 400 days is about 13.1 months; priced in whole months, that is 14.
Common mistake

Weeks against a monthly rate

The programme is often in weeks and the costs per month. Multiplying weeks by a monthly cost prices the site four times over; the error is large enough to stop a tender review, if anyone looks.

Example. 57 weeks x 20,000 per month is 1,140,000, not 280,000.

Preliminaries of a smaller job

Different numbers from your task.

Not to scale
The problem
  • Time for Completion 400 days: 14 whole months.
  • Running cost USD20,000 per month; fixed items USD60,000.
Step 1 of 1

Preliminaries

Total preliminaries?

14 x USD20,000 + USD60,000 = USD340,000.

In short. Fixed once; time-related every month of the Time for Completion.

Check yourself

Question 1 of 3

Site welfare cabins hired by the month are:

  • Right.

  • They cost every month.

  • They are not part of any item.

Question 2 of 3

Where does the estimator read the period from?

  • Right.

  • That ends before the site opens.

  • The site is closed by then.

Question 3 of 3

300 days, 25,000 per month, priced in whole months; fixed 40,000. Preliminaries?

10 x 25,000 + 40,000 = 290,000.