What preliminaries are
Preliminaries, also called site overheads or general requirements, are the costs of the site rather than of any one item of work: management, welfare, cranes, hoarding, temporary power. Some are paid once (set-up, removal); most are paid every month the site runs.
- Fixed USD60,000
- Time-related USD280,000