Theory before task 4 · 6 min

Provisional sums

Provisional sums go in as stated

After this lecture you can

  1. Say what a provisional sum is and who decides its use.
  2. Enter provisional sums as stated.
  3. Assemble the net cost of a tender.
1 / 3

The client's allowance in your tender

A provisional sum is an amount the client writes into the bill for work it cannot yet define. Every bidder carries it unchanged. Under FIDIC 13.4 it is spent only as the Engineer instructs, and the Contractor is paid for what is actually instructed, not for the sum.

Example. A bill with 500,000 of measured work, 150,000 of preliminaries and 200,000 of provisional sums has a net cost of 850,000.
USD500,000USD150,000USD200,000
  • Measured work USD500,000
  • Preliminaries USD150,000
  • Provisional sums USD200,000
2 / 3

Why bidders may not change it

The client compares tenders on the work they price. Equal provisional sums keep that comparison fair; a bidder who edits one has changed the tender form, and many clients reject such a bid as non-compliant.

Example. Practice differs by country in how a non-compliant bid is treated; the common rule is that the sum stands.
Common mistake

A cheaper offer in place of the sum

A subcontractor's lower price for the same services is tempting. It does not belong on the provisional sum line: the work is not yet defined, and the Engineer may instruct it differently. Keep the offer for after award.

Example. Replacing 200,000 with an offer of 170,000 makes the bid look 30,000 cheaper on paper only.

Net cost of a smaller job

Different numbers from your task.

Not to scale
The problem
  • Measured work USD500,000; preliminaries USD150,000.
  • Provisional sums in the tender documents USD200,000.
Step 1 of 1

Net cost

Net cost of the tender?

USD500,000 + USD150,000 + USD200,000 = USD850,000.

In short. Measured work, preliminaries and provisional sums as stated make the net cost.

Check yourself

Question 1 of 3

Who decides how a provisional sum is spent?

  • Right.

  • Not without an instruction.

  • Offers do not decide it.

Question 2 of 3

The services are later instructed for less than the sum. The Contractor is paid:

  • Right.

  • The sum is an allowance, not a price.

  • Instructed work is paid.

Question 3 of 3

Measured work 720,000, preliminaries 210,000, provisional sums 95,000. Net cost?

720,000 + 210,000 + 95,000 = 1,025,000.