The client's allowance in your tender
A provisional sum is an amount the client writes into the bill for work it cannot yet define. Every bidder carries it unchanged. Under FIDIC 13.4 it is spent only as the Engineer instructs, and the Contractor is paid for what is actually instructed, not for the sum.
- Measured work USD500,000
- Preliminaries USD150,000
- Provisional sums USD200,000