Theory before task 5 · 8 min

Mark-ups once, and the tender sum

Mark-ups added once: the tender sum

After this lecture you can

  1. Add overheads, risk and profit on the running total.
  2. Explain how the margin reaches the rates of a remeasured contract.
  3. Read the tender sum from the bill.
1 / 3

Three mark-ups, three reasons

Head office overheads pay for the company behind the site: estimating, accounts, management. A risk allowance covers what the company carries under the contract and cannot price line by line. Profit is the return. Each sits on the running total, so profit is earned on overheads and risk too.

Example. Net cost 2,000,000; overheads 5 %, risk 2 %, profit 4 %, each on the running total.
+USD2,000,0001+USD100,0002+USD42,0003+USD85,6804USD2,227,6805
  • 1 Net cost
  • 2 Overheads
  • 3 Risk
  • 4 Profit
  • 5 Tender sum
2 / 3

The margin in a remeasured contract

Under the FIDIC Red Book the work is paid at measured quantity times the bill rate, so the rates you submit must recover the margin. Estimators either spread the mark-ups into the rates by one factor at the end, or carry them as one adjustment item the client accepts. Practice differs by client; the rule that does not differ is once, not twice.

Example. Spread by a factor of 1.11384, a net rate of 50.00 is submitted at 55.69.
Common mistake

The default base

A new markup row often starts on the sum of positions. Left there, every mark-up sits on the net cost alone, and the profit earns nothing on the overheads and risk. Check each row's Base before you read the Grand Total.

Example. On 2,000,000 at 5 %, 2 % and 4 %: 2,220,000 on the net cost, 2,227,680 on the running total.

Tender sum of a smaller job

Different numbers from your task.

Not to scale
The problem
  • Net cost USD2,000,000.
  • Overheads 5%, risk 2%, profit 4%, each on the running total.
Step 1 of 2

Overheads and risk

Running total after risk?

USD2,000,000 x 1.05 x 1.02 = USD2,142,000.

Step 2 of 2

Profit

Tender sum?

USD2,142,000 x 1.04 = USD2,227,680.

In short. Each mark-up on the running total; the last total is the tender sum.

Check yourself

Question 1 of 3

Which Base makes profit sit on overheads and risk too?

  • Right.

  • That is the net cost alone.

  • A percentage needs a base.

Question 2 of 3

Does the order of the three percentage rows change the tender sum?

  • Right. Each amount changes, the total does not.

  • The product is the same in any order.

  • Same product.

Question 3 of 3

Net cost 1,500,000; overheads 4 % and profit 5 %, on the running total. Tender sum?

1,500,000 x 1.04 x 1.05 = 1,638,000.