Cheat sheet
Remeasure, claim and get paid (Australia, AS 4000)
Every rule of the course on one page: how each figure is built, the mistake people usually make, and where it comes up at work. Print it or keep it open while you work.
- Rule
- A recess is not a void. It lowers the area and adds no edge. A void of 0.50 m² or less is neither deducted nor formed.
- How it is built
- Net area = Overall rectangle − Recess − Voids over the threshold
- Concrete, line 3.1 = Net area, line 3.2 × Slab thickness
- Edge formwork, line 3.3 = Perimeter + Girth of each deducted void
- Reinforcement, line 3.4 = Bar schedule in kilograms ÷ 1,000
- Usual mistake
- A void of 0.50 m² or less is not deducted. Each penetration is 0.09 m².
- At work
- Quantity surveyors measure each pour from the drawings before the monthly claim, line by line against the bill.
- Rule
- A remeasured trade is rate times what is measured. The value to date is all three sections, not this month's slab alone.
- How it is built
- Section 3 total = Line 3.2 rate × net area + the other three lines
- Trade to date = Section 1 + Section 2 + Section 3
- Overstatement = Draft's figure − Trade to date
- Usual mistake
- That is this month's section only. The trade value to date carries the footings and the columns as well.
- At work
- Before a claim goes out, the QS checks every trade the site team rated by eye against the measured bill.
- Rule
- A variation is priced on what changes. Contract rates where they apply, agreed rates where they do not, one margin on the total.
- How it is built
- Extra concrete = Thickened area × Added depth
- Before the margin = Concrete and steel at bill rates + Step and trimming at agreed rates
- Value of variation 14 = Before the margin × (1 + margin)
- Usual mistake
- That is the whole 300 mm slab over the plant deck. The bill already pays for the first 220 mm.
- At work
- The Superintendent directs changes every week; the contractor prices each from bill rates and agreed rates.
- Rule
- A claim line carries the movement. Value to date less what earlier claims certified; GST goes on once, at the foot.
- How it is built
- Line of a trade = Value to date − Certified in claims 1 to 6
- Claim excluding GST = Line PR + Line CS + other trades and VO
- Total claimed = Claim excluding GST × (1 + GST rate)
- Usual mistake
- That is the remeasured trade value to date. Take off what was certified in claims 1 to 6.
- At work
- Every month the contractor serves a payment claim; under the Act it starts a clock the client cannot ignore.
- Rule
- Retention comes off the value; GST goes on the same value. The percentages differ, so they do not cancel.
- How it is built
- Retention on this claim = Claim excluding GST × Retention rate
- Amount payable = Due after retention + GST on the full claim
- Retention still to deduct = Cap − Retention held after claim 6 − This claim's retention
- Usual mistake
- The GST has been charged on the value after retention. The taxable value is the full value of the work.
- At work
- Contractors track retention claim by claim against the cap, because it comes back only at completion.
- Rule
- The Act's clock beats the contract's. A business day skips weekends, public holidays and 27 to 31 December.
- How it is built
- Schedule due = Service + business days, no weekends, holidays or 27 to 31 December
- Last day for adjudication = Schedule date + ten business days
- Shortfall = Payable as claimed − Payable as scheduled
- Usual mistake
- Both periods have been counted as calendar days. The Act counts business days, twice over here.
- At work
- Contract administrators diary every statutory date the day a claim is served, holidays and the Christmas shutdown included.