Cheat sheet

Remeasure, claim and get paid (Australia, AS 4000)

Every rule of the course on one page: how each figure is built, the mistake people usually make, and where it comes up at work. Print it or keep it open while you work.

Task 1

Remeasure the Level 1 slab for the claim

Theory (11 min)
Rule
A recess is not a void. It lowers the area and adds no edge. A void of 0.50 m² or less is neither deducted nor formed.
How it is built
  • Net area = Overall rectangle − Recess − Voids over the threshold
  • Concrete, line 3.1 = Net area, line 3.2 × Slab thickness
  • Edge formwork, line 3.3 = Perimeter + Girth of each deducted void
  • Reinforcement, line 3.4 = Bar schedule in kilograms ÷ 1,000
Usual mistake
A void of 0.50 m² or less is not deducted. Each penetration is 0.09 m².
At work
Quantity surveyors measure each pour from the drawings before the monthly claim, line by line against the bill.

Task 2

Price the bill and value the trade to date

Theory (10 min)
Rule
A remeasured trade is rate times what is measured. The value to date is all three sections, not this month's slab alone.
How it is built
  • Section 3 total = Line 3.2 rate × net area + the other three lines
  • Trade to date = Section 1 + Section 2 + Section 3
  • Overstatement = Draft's figure − Trade to date
Usual mistake
That is this month's section only. The trade value to date carries the footings and the columns as well.
At work
Before a claim goes out, the QS checks every trade the site team rated by eye against the measured bill.

Task 3

Value the slab thickening as a variation

Theory (11 min)
Rule
A variation is priced on what changes. Contract rates where they apply, agreed rates where they do not, one margin on the total.
How it is built
  • Extra concrete = Thickened area × Added depth
  • Before the margin = Concrete and steel at bill rates + Step and trimming at agreed rates
  • Value of variation 14 = Before the margin × (1 + margin)
Usual mistake
That is the whole 300 mm slab over the plant deck. The bill already pays for the first 220 mm.
At work
The Superintendent directs changes every week; the contractor prices each from bill rates and agreed rates.

Task 4

Payment claim 7 for the named month

Theory (12 min)
Rule
A claim line carries the movement. Value to date less what earlier claims certified; GST goes on once, at the foot.
How it is built
  • Line of a trade = Value to date − Certified in claims 1 to 6
  • Claim excluding GST = Line PR + Line CS + other trades and VO
  • Total claimed = Claim excluding GST × (1 + GST rate)
Usual mistake
That is the remeasured trade value to date. Take off what was certified in claims 1 to 6.
At work
Every month the contractor serves a payment claim; under the Act it starts a clock the client cannot ignore.

Task 5

Retention, security and what is actually payable

Theory (10 min)
Rule
Retention comes off the value; GST goes on the same value. The percentages differ, so they do not cancel.
How it is built
  • Retention on this claim = Claim excluding GST × Retention rate
  • Amount payable = Due after retention + GST on the full claim
  • Retention still to deduct = Cap − Retention held after claim 6 − This claim's retention
Usual mistake
The GST has been charged on the value after retention. The taxable value is the full value of the work.
At work
Contractors track retention claim by claim against the cap, because it comes back only at completion.

Task 6

The payment schedule and the statutory clock

Theory (12 min)
Rule
The Act's clock beats the contract's. A business day skips weekends, public holidays and 27 to 31 December.
How it is built
  • Schedule due = Service + business days, no weekends, holidays or 27 to 31 December
  • Last day for adjudication = Schedule date + ten business days
  • Shortfall = Payable as claimed − Payable as scheduled
Usual mistake
Both periods have been counted as calendar days. The Act counts business days, twice over here.
At work
Contract administrators diary every statutory date the day a claim is served, holidays and the Christmas shutdown included.