Cheat sheet
Bill-of-quantities pricing in practice: GB/T 50500-2024 (China)
Every rule of the course on one page: how each figure is built, the mistake people usually make, and where it comes up at work. Print it or keep it open while you work.
- Rule
- First read which prices hold VAT, then the base the contract gives overhead and profit.
- How it is built
- Price net of VAT = Price including VAT ÷ (1 + VAT rate)
- Each cost = Norm quantity × Price net of VAT
- Beam 01.05 unit rate = Labour + materials + machinery + (Labour + machinery) × fee and profit rates
- Bill direct cost = Column 01.04 + Beam 01.05 and the other lines
- Usual mistake
- Divide the prices with VAT by 1.13: the rate is built on prices without VAT.
- At work
- Cost engineers build every bid rate this way: norm quantities times net prices, then fee and profit on the contract's base.
- Rule
- A charge is taken on the base the contract names, not on the nearest total.
- How it is built
- Measured works = Quantities of section 01 × Their unit rates
- Work-safety measures charge = Measured works × Contract rate
- Measures = Scaffolding + formwork + Work-safety measures charge
- Usual mistake
- The base is the measured works only.
- At work
- Both the tender ceiling price and the bid list measures separately; the reviewer checks the safety charge base first.
- Rule
- First ask which layer already holds each cost, then decide whether a row belongs.
- How it is built
- the three sections = Measured works + measures + other items
- VAT = the three sections × VAT rate
- Price including VAT = the three sections + VAT
- Usual mistake
- Social insurance and the housing fund are already in the rates; the VAT base is the three sections only.
- At work
- Every bid adds VAT at the end of the bill; since the 2024 standard a reviewer first checks that no fees are counted twice.
- Rule
- Each deduction has its own base: find it in the contract, do not trust the draft.
- How it is built
- Value of work this period = Each line done this period × Composite rate
- Retention = Value of work this period × Retention rate
- Advance recovery = Period value with VAT × Recovery rate
- Amount payable = Period value with VAT − Advance recovery − Retention
- Usual mistake
- The advance was paid on a tax-inclusive base, so the recovery base includes tax.
- At work
- Site cost engineers prepare an interim claim every period; the client checks the base of each deduction.
- Rule
- Down for an increase, up for a decrease, on the items over the limit only. An increase in two parts, a decrease on the whole remainder.
- How it is built
- Increased item value = Limit quantity × original rate + Excess × original rate × 95 %
- Reduced item value = reviewed qty × Original rate × 105 %
- Variation amount = Both adjusted values − Both contract values
- Usual mistake
- The 644 m³ up to the limit stay at the old rate; only the excess 56 m³ takes 95 %.
- At work
- At the final account both sides remeasure each item; items past the limit are repriced by the contract.