Bill-of-quantities pricing in practice: GB/T 50500-2024 (China)

Every rule of the course on one page: how each figure is built, the mistake people usually make, and where it comes up at work. Print it or keep it open while you work.

Task 1

Composite unit rate: beams and columns

Theory (11 min)
Rule
First read which prices hold VAT, then the base the contract gives overhead and profit.
How it is built
  • Price net of VAT = Price including VAT ÷ (1 + VAT rate)
  • Each cost = Norm quantity × Price net of VAT
  • Beam 01.05 unit rate = Labour + materials + machinery + (Labour + machinery) × fee and profit rates
  • Bill direct cost = Column 01.04 + Beam 01.05 and the other lines
Usual mistake
Divide the prices with VAT by 1.13: the rate is built on prices without VAT.
At work
Cost engineers build every bid rate this way: norm quantities times net prices, then fee and profit on the contract's base.

Task 2

Measured works and measures

Theory (10 min)
Rule
A charge is taken on the base the contract names, not on the nearest total.
How it is built
  • Measured works = Quantities of section 01 × Their unit rates
  • Work-safety measures charge = Measured works × Contract rate
  • Measures = Scaffolding + formwork + Work-safety measures charge
Usual mistake
The base is the measured works only.
At work
Both the tender ceiling price and the bid list measures separately; the reviewer checks the safety charge base first.

Task 3

VAT on the three sections

Theory (9 min)
Rule
First ask which layer already holds each cost, then decide whether a row belongs.
How it is built
  • the three sections = Measured works + measures + other items
  • VAT = the three sections × VAT rate
  • Price including VAT = the three sections + VAT
Usual mistake
Social insurance and the housing fund are already in the rates; the VAT base is the three sections only.
At work
Every bid adds VAT at the end of the bill; since the 2024 standard a reviewer first checks that no fees are counted twice.

Task 4

Interim payment and advance recovery

Theory (10 min)
Rule
Each deduction has its own base: find it in the contract, do not trust the draft.
How it is built
  • Value of work this period = Each line done this period × Composite rate
  • Retention = Value of work this period × Retention rate
  • Advance recovery = Period value with VAT × Recovery rate
  • Amount payable = Period value with VAT − Advance recovery − Retention
Usual mistake
The advance was paid on a tax-inclusive base, so the recovery base includes tax.
At work
Site cost engineers prepare an interim claim every period; the client checks the base of each deduction.

Task 5

Quantity deviation over 15 %

Theory (11 min)
Rule
Down for an increase, up for a decrease, on the items over the limit only. An increase in two parts, a decrease on the whole remainder.
How it is built
  • Increased item value = Limit quantity × original rate + Excess × original rate × 95 %
  • Reduced item value = reviewed qty × Original rate × 105 %
  • Variation amount = Both adjusted values − Both contract values
Usual mistake
The 644 m³ up to the limit stay at the old rate; only the excess 56 m³ takes 95 %.
At work
At the final account both sides remeasure each item; items past the limit are repriced by the contract.