Ask why until you reach a step you can change
The gang poured because the pump arrived. The pump arrived because the concrete was booked on Thursday. It was booked before the steel was finished because the plant needs 48 hours. Nothing tied the booking to the release of H2. That last answer is a step in the process, and the preventive action changes it: no pour confirmed with the plant until H2 is signed and the Supervisor told. Quality management standards such as ISO 9001 (clause 10.2) ask for exactly this: correct the nonconformity, find its cause, act so it does not recur.