Five parts of a Defect's cost
The repair crew is the visible part. Before it come the survey and the engineer's time; around it come access, and behind it comes time: every working day the critical path waits, the site's time-related overheads (supervision, welfare, cabins, plant on hire) keep running. A full NCR cost adds all five.
- 1 Survey
- 2 Engineer
- 3 Repair
- 4 Access
- 5 Standing time
- 6 Total