OpenConstruction Academy
Sign in / Register
EN

Theory before task 1 · 8 min

A sub bid on bid day: record it line by line

The 1:05 phone bid: record it as quoted

Course introduction

After this lecture you can

  1. Read a subcontractor's scope sheet line by line.
  2. Record a phoned bid exactly as quoted, blanks included.
  3. Check a sub can be carried on a public bid before you rely on it.
1 / 4

What a scope sheet is

Before bid day the GC sends each trade a scope sheet: the work split into numbered lines, each tied to a spec section. Subs price each line, so their numbers can be compared line against line instead of as one lump. On a drywall package the lines follow the specification: framing, board and finish, special finishes, insulation, and the joints where a rated wall meets the floor above.

Example. On this job the drywall sheet has five lines, DW-01 to DW-05.
2 / 4

The last hour

Most sub prices arrive in the last hours before the deadline, many by phone. Each one is written down line by line as it is said, with anything the sub excludes in its own words. The estimator does not improve, correct or complete a price while recording it: that comes later, on the leveling sheet, where everyone can see what was changed and why.

Example. A painting bid on the same job, taken by phone in three lines.
$61,400$27,800
  • Walls and ceilings, two coats $61,400
  • Doors and frames $27,800
  • Exterior trim $7,100
3 / 4

Is the sub allowed on this job?

On a California public works bid every sub you carry must hold the right state license and be registered with the Department of Industrial Relations. A price from a sub who cannot be listed is not a price you can use. A one-minute check on both public lookups belongs before you carry the number, not after the bid is opened.

Example. Drywall in California is licensed work: the classification is C-9.
Common mistake

Filling the blank while you record

A sub leaves a line blank and the estimator types in another bidder's price 'so the totals compare'. Now the record says the sub offered work it never offered, and nobody can see that a plug was used. Record the blank. Price it on the leveling sheet, in its own column, where the chief estimator can see it.

Example. A blank in the bid record is a fact; a plug on the leveling sheet is a decision.

The painting bid by phone

Same bid, a different package: painting, phoned in at 12:40.

Not to scale
The problem
  • Walls and ceilings: $61,400.
  • Doors and frames: $27,800.
  • Exterior trim: $7,100.
  • Graffiti coating: not priced, 'by others'.
Step 1 of 1

Recorded total

What total do you record for the painter?

$61,400 + $27,800 + $7,100 = $96,300.00.

In short. Record the lines quoted and the line excluded; the excluded one is priced on the leveling sheet, not here.

Check yourself

Question 1 of 2

A sub phones in four of five lines and says 'the fifth is by others'. What do you record?

  • Right.

  • That puts words in the sub's mouth.

  • On bid day a phoned price is recorded.

  • Then nobody can level it line by line.

Question 2 of 2

A sub quotes 118,000, 64,500 and 9,800 and leaves a fourth line blank. What total do you record?

118,000 + 64,500 + 9,800 = 192,300.

Read the source

Free official texts. The lecture cites clause numbers and puts the rules in its own words.

  • CSI MasterFormatcsiresources.org

    The numbering system behind every spec section and scope line on a US bid, such as 09 21 16 for gypsum board.

  • CSLB: Check a Licensecslb.ca.gov

    Confirm a phoned-in sub holds an active California license, C-9 for drywall, before you carry its number.

  • DIR: Public works contractor registrationdir.ca.gov

    A sub that is not registered with the Department of Industrial Relations cannot be used on public work.