What a scope sheet is
Before bid day the GC sends each trade a scope sheet: the work split into numbered lines, each tied to a spec section. Subs price each line, so their numbers can be compared line against line instead of as one lump. On a drywall package the lines follow the specification: framing, board and finish, special finishes, insulation, and the joints where a rated wall meets the floor above.