Theory before task 2 · 9 min

Scope gaps and plugs

Open the bids and plug the gap

After this lecture you can

  1. Spot a blank or excluded line in a sub bid.
  2. Plug the gap on the leveling sheet by a stated rule.
  3. Level every bid on one common scope.
1 / 4

Why the low number has a hole in it

A sub that wants to be low reads the scope narrowly. The cheapest drywall bid often finishes everything to Level 4, the normal finish for flat paint, and leaves out the Level 5 skim coat the specification asks for where light rakes along a corridor wall. The price is lower because the scope is smaller.

Example. Level 5 means a skim coat over the whole surface; Level 4 does not have one.
2 / 4

The plug

If you cannot get the sub to confirm the missing line before the deadline, you price it yourself: that price is the plug. It goes on the leveling sheet, next to the sub's own prices, never into its bid. A cautious rule is to plug with the highest price another bidder carried for the same line, because an unconfirmed price that turns out higher is an overrun you own.

Example. An acoustical ceiling bid on the same job that left the seismic bracing blank.
Ceiling bid as submitted, lines priced$148,200.00
Plug for the blank line$11,600.00
Leveled bid$159,800.00
3 / 4

One common scope

Leveling means every bid covers the same lines. Plug what is missing; take out what is carried elsewhere. A line bought from another trade, such as head-of-wall fire joints bought from the firestopping sub, comes out of every drywall bid, even from the ones that priced it.

Example. On this job the common scope is DW-01 to DW-04.
Common mistake

Plugging with the lowest price

The lowest price for the missing line makes the gap look small and keeps the low bidder low. It is the most optimistic guess available. Use the rule written for the bid, and if the result is close, call the sub again before the deadline.

Example. A plug is a risk allowance, not a discount.

The ceiling bid with a gap

Same bid, the acoustical ceilings package.

Not to scale
The problem
  • Ceiling bid: $148,200 for the lines it priced; seismic bracing left blank.
  • Other bidders carried bracing at $11,600 and $9,400.
  • Rule: plug with the highest price another bidder carried.
Step 1 of 2

The plug

Which plug do you use?

The higher of $11,600 and $9,400: $11,600.00.

Step 2 of 2

Leveled

What is the leveled ceiling bid?

$148,200 + $11,600.00 = $159,800.00.

In short. Plug on the sheet, by the rule, and compare only once every bid covers the same lines.

Check yourself

Question 1 of 2

A bid leaves a required line blank and the sub will not answer. What goes on the leveling sheet?

  • Right.

  • It becomes your cost if you carry that sub.

  • The most optimistic guess.

  • Then you compare different scopes.

Question 2 of 2

A flooring bid is 201,300 without the moisture testing line. Others carried testing at 3,900 and 5,200. Plug with the highest: leveled bid?

201,300 + 5,200 = 206,500.

Read the source

Free official texts. The lecture cites clause numbers and puts the rules in its own words.

  • Gypsum Associationgypsum.org

    Publisher of GA-214, the industry's description of the five levels of gypsum board finish that drywall bids refer to.

  • CSI MasterFormatcsiresources.org

    Why a joint at the head of a rated wall can sit in 07 84 00 while the wall itself is in 09: two sections, two possible trades.