Theory before task 3 · 7 min

Permits to work

Permits to work for the week

After this lecture you can

  1. Say what a permit to work adds to a risk assessment.
  2. Decide from a permit rule which jobs need a permit.
  3. Issue a permit with its checks.
1 / 3

A written authority for one job

A permit to work is a written authority to do one high-risk job, in one place, for one shift, after named checks are done: a fire watch for hot work, a gas test for a confined space, an isolation for electrical work. It is issued, activated, and closed when the area is safe again. The jobs that need one are named in the contractor's rules, which FIDIC 4.8 expects the contractor to set out.

Example. A roofer's torch-on membrane needs a hot work permit each day, with a fire watch after the torch is off.
2 / 3

The rule decides, not the feeling

Permit rules name kinds of work: hot work, confined spaces, electrical isolation, unprotected edges, mobile crane lifts, deep excavations. Many dangerous jobs are not on the list because their risk assessment already controls them; some quiet jobs are, because one forgotten step there is catastrophic. Rules differ between companies and countries; read the one for your site.

Example. Grinding a steel bracket is hot work: the sparks start fires as a flame does.
Common mistake

A permit for everything

When every job needs a permit, the permits become paperwork and the checks stop meaning anything. Keep permits for the jobs the rule names and make each check real.

Example. Twenty permits a day signed in five minutes protect nobody.

Which jobs need a permit

Different jobs from your task.

Not to scale
The problem
  • Jobs: welding a balcony bracket, grinding a pipe end, entering a pump sump, painting a stairwell, laying blocks inside the edge protection.
  • The rule names hot work and confined spaces: 2 hot work jobs, 1 confined space.
Step 1 of 1

Count

How many jobs need a permit?

2 + 1 = 3.

In short. Match each job to a line of the rule; then make every check real.

Check yourself

Question 1 of 3

What does a permit add to a risk assessment?

  • Right.

  • It sits on top of it.

  • A permit is about safety, not money.

Question 2 of 3

Is cutting a bar with a disc cutter hot work?

  • Right.

  • Sparks start fires too.

  • The place does not change what the work is.

Question 3 of 3

Of six jobs, two are hot work, one is an electrical isolation, three are covered by risk assessments only. Permits needed?

2 + 1 = 3.

Read the source

Free official texts. The lecture cites clause numbers and puts the rules in its own words.