Cheat sheet
Procurement: compare quotes and buy steel (UK)
Every rule of the course on one page: how each figure is built, the mistake people usually make, and where it comes up at work. Print it or keep it open while you work.
- Rule
- Compare on landed cost, and only quotes that arrive in time.
- How it is built
- Landed cost of the order = Tonnes × Bar rate with cutting and bending + Delivery
- Usual mistake
- You picked the lowest bar rate among the quotes on time. Its cutting and bending is extra, which makes it dearer delivered.
- At work
- Buyers compare every materials quote this way before a purchase order goes out.
- Rule
- Goods carry VAT; construction services reverse it. Supply-only steel is goods.
- How it is built
- VAT on the order = Order net × Standard rate
- Usual mistake
- You applied the reverse charge to a supply of goods. It covers construction services; supply-only steel carries VAT at the standard rate.
- At work
- Every order the buyer issues states its VAT treatment; accounts check the invoice against it.
- Rule
- Record what you counted, never what the note claims.
- How it is built
- Shortfall at the order rate = Tonnes ordered − Tonnes received × Order rate per tonne
- Usual mistake
- The missing steel is right; the delivery charge is added to it. The one load did arrive.
- At work
- Site staff count every delivery against the note before signing; the buyer records the receipt.
- Rule
- Pay what order, receipt and invoice all support. Enter the invoice as billed; hold the rest.
- How it is built
- Approve for payment now = Value received at order rates + VAT at the standard rate
- Usual mistake
- You approved the invoice as billed. Pay only what the receipt supports; hold the missing bundle.
- At work
- Accounts pay a supplier invoice only after the buyer confirms order, receipt and invoice agree.
- Rule
- Reverse charge moves the VAT to you; it does not remove it.
- How it is built
- VAT you account for to HMRC = Fixing order net × Standard rate
- Usual mistake
- Reverse charge moves the VAT to you; it does not remove it. You account for it and, normally, reclaim it in the same return.
- At work
- Every labour subcontract order on a UK site is checked for the reverse charge and CIS before it is issued.