Cheat sheet
Developer cost check: can we pay the asking price? (UAE)
Every rule of the course on one page: how each figure is built, the mistake people usually make, and where it comes up at work. Print it or keep it open while you work.
- Rule
- Cost follows enclosed floor. Measure to the inside face of the external wall, every level; open balconies stay out.
- How it is built
- Gross internal area = Ground floor + 12 × typical floor + Roof level
- Usual mistake
- The balconies went in. Open balconies are outside the external wall, so they are not gross internal area.
- At work
- At feasibility a cost manager prices floor plates against benchmark rates before any drawing is detailed.
- Rule
- Profit sits on the site set-up too. Preliminaries on the works; overheads and profit on works plus preliminaries; VAT out.
- How it is built
- Works cost estimate = Grand Total
- Usual mistake
- Overheads and profit sat on the sum of positions only. Set its base to the running total, so it covers the preliminaries too.
- At work
- The developer's cost manager adds the contractor's layers in NRM1 order and keeps recoverable VAT out.
- Rule
- Risk goes last, on everything. Fees on the works cost estimate, quotes as fixed sums, risk on the base cost estimate.
- How it is built
- Cost limit = Grand Total
- Usual mistake
- Risk was taken on the works cost estimate only. It sits on the base cost estimate: fees and other costs too.
- At work
- The cost limit goes into the board paper with what it excludes written next to it: inflation and VAT.
- Rule
- The bank funds the deepest point. Interest runs only while the balance is negative, half-year by half-year.
- How it is built
- Finance cost = 3.5 % × Σ negative closing balances
- Usual mistake
- The peak was charged for every half-year. Charge each half-year on its own closing balance.
- At work
- The cost manager spreads the cost limit, the sales team gives escrow releases, and the bank reads the lowest point.
- Rule
- The land takes what is left. GDV less cost, sales, finance and profit; divide out the fee; compare with the asking price.
- How it is built
- Residual land value = GDV − Cost limit − Sales − Finance − Profit
- Land price = Residual ÷ 1.04
- Usual mistake
- The registration fee is still inside. Divide by 1.04 to get the price for the land itself.
- At work
- The board paper shows the residual, the asking price, the gap and the profit at the asking price, then a recommendation.