Cheat sheet

Developer cost check: can we pay the asking price? (UAE)

Every rule of the course on one page: how each figure is built, the mistake people usually make, and where it comes up at work. Print it or keep it open while you work.

Task 1

The floor area the board will price

Theory (7 min)
Rule
Cost follows enclosed floor. Measure to the inside face of the external wall, every level; open balconies stay out.
How it is built
  • Gross internal area = Ground floor + 12 × typical floor + Roof level
Usual mistake
The balconies went in. Open balconies are outside the external wall, so they are not gross internal area.
At work
At feasibility a cost manager prices floor plates against benchmark rates before any drawing is detailed.

Task 2

What a contractor would charge to build it

Theory (8 min)
Rule
Profit sits on the site set-up too. Preliminaries on the works; overheads and profit on works plus preliminaries; VAT out.
How it is built
  • Works cost estimate = Grand Total
Usual mistake
Overheads and profit sat on the sum of positions only. Set its base to the running total, so it covers the preliminaries too.
At work
The developer's cost manager adds the contractor's layers in NRM1 order and keeps recoverable VAT out.

Task 3

The cost limit the board signs

Theory (8 min)
Rule
Risk goes last, on everything. Fees on the works cost estimate, quotes as fixed sums, risk on the base cost estimate.
How it is built
  • Cost limit = Grand Total
Usual mistake
Risk was taken on the works cost estimate only. It sits on the base cost estimate: fees and other costs too.
At work
The cost limit goes into the board paper with what it excludes written next to it: inflation and VAT.

Task 4

How deep the bank has to go

Theory (9 min)
Rule
The bank funds the deepest point. Interest runs only while the balance is negative, half-year by half-year.
How it is built
  • Finance cost = 3.5 % × Σ negative closing balances
Usual mistake
The peak was charged for every half-year. Charge each half-year on its own closing balance.
At work
The cost manager spreads the cost limit, the sales team gives escrow releases, and the bank reads the lowest point.

Task 5

Go, no-go, or a counter-offer

Theory (9 min)
Rule
The land takes what is left. GDV less cost, sales, finance and profit; divide out the fee; compare with the asking price.
How it is built
  • Residual land value = GDV − Cost limit − Sales − Finance − Profit
  • Land price = Residual ÷ 1.04
Usual mistake
The registration fee is still inside. Divide by 1.04 to get the price for the land itself.
At work
The board paper shows the residual, the asking price, the gap and the profit at the asking price, then a recommendation.