От офертата до първата оценка (Великобритания, JCT)

You are the quantity surveyor for the main contractor. In five tasks you take a four-storey office from the priced bill to the first monthly payment and the first change.

Започнете задача 1

The site: a four-storey concrete frame office under construction.Измислен проект
Tallowgate WorksFour-storey office
Building
Four-storey office, shell and core
Contract
JCT SBC/Q 2024, with bills of quantities
Story
June to October 2026
Работа в ERP
Задачи: 5, около 1 ч 45 мин

Кой какво предава на кого

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Идва при вас

  • EstimatorYour firm
    • Net ratesЗадача 1
  • Three dry lining firmsSubcontract bidders
    • BidsЗадача 3
  • ArchitectIssues instructions
    • InstructionЗадача 5
ВиеQuantity surveyor, main contractor

Тръгва от вас

    • TenderЗадача 2
    • ValuationЗадача 4
    • VariationЗадача 5
    Client's QSFor the developer
    • OrderЗадача 3
    Dry lining subcontractorLowest complete bid

Проектът и хората са измислени. Портретите са генерирани.

Вашият път през проекта

Two tasks at tender, one to buy the work, two on site. Each task you pass adds a line to your job file.

  1. At tender

    Задача 1 · 15 мин

    Остойностете пакета сухо строителство

    Вашият резултат
    The dry lining allowance
    Документ
    Bill of quantities, dry lining lines
    В ERP
    Bill of Quantities
  2. At tender

    Задача 2 · 20 мин

    Изградете общата сума на офертата

    Вашият резултат
    The tender sum, without VAT
    Документ
    Your firm's mark-ups on the bill
    В ERP
    Bill of Quantities, Markups
  3. Buying the work

    Задача 3 · 25 мин

    Изравнете офертите за сухо строителство и възложете

    Вашият резултат
    The dry lining subcontract
    Документ
    Levelled bids and the award decision
    В ERP
    Bid Management
  4. On site

    Задача 4 · 20 мин

    Междинна оценка 1 (септември)

    Вашият резултат
    Interim Valuation 1 and its VAT
    Документ
    Progress claim for September
    В ERP
    Contracts, Progress Claims
  5. On site

    Задача 5 · 25 мин

    Оценете промяна 01 (AI 07)

    Вашият резултат
    Variation 01 and the new contract sum
    Документ
    Architect's Instruction AI 07
    В ERP
    Variations

How a rate becomes a payment

Each step below is one task, in the order the money moves. Task 3, buying the dry lining, sits between the tender sum and the first valuation.

Bill lines at net rates
Задача 1Direct costQuantity times net rate, line by line. Cost only.
Overheads and profitPreliminariesDirect cost
Задача 2Tender sumPreliminaries, overheads and profit go on once, to the whole bill. No VAT.
Still to buildRetentionWork done
Задача 4Monthly valuationWork done to date, less retention. VAT is added to what is paid.
Variation 01Contract sum
Задача 5VariationChanged work, valued at the bill's rates, moves the contract sum.

В синьо е това, което задачата добавя; в сиво е пренесеното отпреди.

Накратко. Rates stay net. Mark-ups go on once. VAT follows each payment.