Panimula ng kurso · 3 min

Mula tender hanggang unang valuation (UK, JCT)

You are the quantity surveyor for the main contractor. In five tasks you take a four-storey office from the priced bill to the first monthly payment and the first change.

Simulan ang gawain 1

The site: a four-storey concrete frame office under construction.Kathang-isip na proyekto
Tallowgate WorksFour-storey office
Building
Four-storey office, shell and core
Contract
JCT SBC/Q 2024, with bills of quantities
Story
June to October 2026
Trabaho sa ERP
5 gawain, mga 1 oras 45 min

Sino ang nagbibigay ng ano kanino

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Dumarating sa iyo

  • EstimatorYour firm
    • Net ratesGawain 1
  • Three dry lining firmsSubcontract bidders
    • BidsGawain 3
  • ArchitectIssues instructions
    • InstructionGawain 5
IkawQuantity surveyor, main contractor

Lumalabas sa iyo

    • TenderGawain 2
    • ValuationGawain 4
    • VariationGawain 5
    Client's QSFor the developer
    • OrderGawain 3
    Dry lining subcontractorLowest complete bid

Kathang-isip ang proyekto at ang mga tao. Gawa ng computer ang mga larawan.

Ang ruta mo sa proyekto

Two tasks at tender, one to buy the work, two on site. Each task you pass adds a line to your job file.

  1. At tender

    Gawain 1 · 15 min

    I-presyo ang dry lining package

    Ang gagawin mo
    The dry lining allowance
    Dokumento
    Bill of quantities, dry lining lines
    Sa ERP
    Bill of Quantities
  2. At tender

    Gawain 2 · 20 min

    Buuin ang tender sum

    Ang gagawin mo
    The tender sum, without VAT
    Dokumento
    Your firm's mark-ups on the bill
    Sa ERP
    Bill of Quantities, Markups
  3. Buying the work

    Gawain 3 · 25 min

    I-level ang mga bid ng dry lining at igawad

    Ang gagawin mo
    The dry lining subcontract
    Dokumento
    Levelled bids and the award decision
    Sa ERP
    Bid Management
  4. On site

    Gawain 4 · 20 min

    Interim Valuation 1 (Setyembre)

    Ang gagawin mo
    Interim Valuation 1 and its VAT
    Dokumento
    Progress claim for September
    Sa ERP
    Contracts, Progress Claims
  5. On site

    Gawain 5 · 25 min

    I-valuate ang Variation 01 (AI 07)

    Ang gagawin mo
    Variation 01 and the new contract sum
    Dokumento
    Architect's Instruction AI 07
    Sa ERP
    Variations

How a rate becomes a payment

Each step below is one task, in the order the money moves. Task 3, buying the dry lining, sits between the tender sum and the first valuation.

Bill lines at net rates
Gawain 1Direct costQuantity times net rate, line by line. Cost only.
Overheads and profitPreliminariesDirect cost
Gawain 2Tender sumPreliminaries, overheads and profit go on once, to the whole bill. No VAT.
Still to buildRetentionWork done
Gawain 4Monthly valuationWork done to date, less retention. VAT is added to what is paid.
Variation 01Contract sum
Gawain 5VariationChanged work, valued at the bill's rates, moves the contract sum.

Asul ang idinadagdag ng gawain; abo ang dala mula sa naunang hakbang.

Sa madaling salita. Rates stay net. Mark-ups go on once. VAT follows each payment.