You are the quantity surveyor for the main contractor. In five tasks you take a four-storey office from the priced bill to the first monthly payment and the first change.

1-тапшырманы баштоо

The site: a four-storey concrete frame office under construction.Ойдон чыгарылган долбоор
Tallowgate WorksFour-storey office
Building
Four-storey office, shell and core
Contract
JCT SBC/Q 2024, with bills of quantities
Story
June to October 2026
ERPдеги иш
Тапшырмалар: 5, болжол менен 1 саат 45 мүн

Ким кимге эмне берет

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Сизге келет

  • EstimatorYour firm
    • Net rates1-тапшырма
  • Three dry lining firmsSubcontract bidders
    • Bids3-тапшырма
  • ArchitectIssues instructions
    • Instruction5-тапшырма
СизQuantity surveyor, main contractor

Сизден кетет

    • Tender2-тапшырма
    • Valuation4-тапшырма
    • Variation5-тапшырма
    Client's QSFor the developer
    • Order3-тапшырма
    Dry lining subcontractorLowest complete bid

Долбоор жана адамдар ойдон чыгарылган. Портреттер генерацияланган.

Долбоор боюнча жолуңуз

Two tasks at tender, one to buy the work, two on site. Each task you pass adds a line to your job file.

  1. At tender

    1-тапшырма · 15 мүн

    Гипсокартон иштеринин пакетин баалаңыз

    Натыйжа
    The dry lining allowance
    Документ
    Bill of quantities, dry lining lines
    ERPде
    Bill of Quantities
  2. At tender

    2-тапшырма · 20 мүн

    Тендер суммасын түзүңүз

    Натыйжа
    The tender sum, without VAT
    Документ
    Your firm's mark-ups on the bill
    ERPде
    Bill of Quantities, Markups
  3. Buying the work

    3-тапшырма · 25 мүн

    Гипсокартон сунуштарын теңдештирип, пакетти бериңиз

    Натыйжа
    The dry lining subcontract
    Документ
    Levelled bids and the award decision
    ERPде
    Bid Management
  4. On site

    4-тапшырма · 20 мүн

    Аралык баалоо (Аралык баалоо 1, сентябрь)

    Натыйжа
    Interim Valuation 1 and its VAT
    Документ
    Progress claim for September
    ERPде
    Contracts, Progress Claims
  5. On site

    5-тапшырма · 25 мүн

    Variation 01 ди баалаңыз (AI 07)

    Натыйжа
    Variation 01 and the new contract sum
    Документ
    Architect's Instruction AI 07
    ERPде
    Variations

How a rate becomes a payment

Each step below is one task, in the order the money moves. Task 3, buying the dry lining, sits between the tender sum and the first valuation.

Bill lines at net rates
1-тапшырмаDirect costQuantity times net rate, line by line. Cost only.
Overheads and profitPreliminariesDirect cost
2-тапшырмаTender sumPreliminaries, overheads and profit go on once, to the whole bill. No VAT.
Still to buildRetentionWork done
4-тапшырмаMonthly valuationWork done to date, less retention. VAT is added to what is paid.
Variation 01Contract sum
5-тапшырмаVariationChanged work, valued at the bill's rates, moves the contract sum.

Көк менен — тапшырма кошкон бөлүк; боз менен — мурунку кадамдан келгени.

Кыскача. Rates stay net. Mark-ups go on once. VAT follows each payment.