Od ponude do prvog obračuna (UK, JCT)

You are the quantity surveyor for the main contractor. In five tasks you take a four-storey office from the priced bill to the first monthly payment and the first change.

Započni zadatak 1

The site: a four-storey concrete frame office under construction.Izmišljeni projekt
Tallowgate WorksFour-storey office
Building
Four-storey office, shell and core
Contract
JCT SBC/Q 2024, with bills of quantities
Story
June to October 2026
Rad u ERP-u
Zadataka: 5, oko 1 h 45 min

Tko kome što predaje

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Dolazi vama

  • EstimatorYour firm
    • Net ratesZadatak 1
  • Three dry lining firmsSubcontract bidders
    • BidsZadatak 3
  • ArchitectIssues instructions
    • InstructionZadatak 5
ViQuantity surveyor, main contractor

Odlazi od vas

    • TenderZadatak 2
    • ValuationZadatak 4
    • VariationZadatak 5
    Client's QSFor the developer
    • OrderZadatak 3
    Dry lining subcontractorLowest complete bid

Projekt i osobe su izmišljeni. Portreti su generirani.

Vaš put kroz projekt

Two tasks at tender, one to buy the work, two on site. Each task you pass adds a line to your job file.

  1. At tender

    Zadatak 1 · 15 min

    Izračunajte cijenu paketa suhe gradnje

    Vaš rezultat
    The dry lining allowance
    Dokument
    Bill of quantities, dry lining lines
    U ERP-u
    Bill of Quantities
  2. At tender

    Zadatak 2 · 20 min

    Sastavite ponudbeni iznos

    Vaš rezultat
    The tender sum, without VAT
    Dokument
    Your firm's mark-ups on the bill
    U ERP-u
    Bill of Quantities, Markups
  3. Buying the work

    Zadatak 3 · 25 min

    Izjednačite ponude za suhu gradnju i dodijelite posao

    Vaš rezultat
    The dry lining subcontract
    Dokument
    Levelled bids and the award decision
    U ERP-u
    Bid Management
  4. On site

    Zadatak 4 · 20 min

    Privremeni obračun 1 (rujan)

    Vaš rezultat
    Interim Valuation 1 and its VAT
    Dokument
    Progress claim for September
    U ERP-u
    Contracts, Progress Claims
  5. On site

    Zadatak 5 · 25 min

    Vrednujte izmjenu 01 (AI 07)

    Vaš rezultat
    Variation 01 and the new contract sum
    Dokument
    Architect's Instruction AI 07
    U ERP-u
    Variations

How a rate becomes a payment

Each step below is one task, in the order the money moves. Task 3, buying the dry lining, sits between the tender sum and the first valuation.

Bill lines at net rates
Zadatak 1Direct costQuantity times net rate, line by line. Cost only.
Overheads and profitPreliminariesDirect cost
Zadatak 2Tender sumPreliminaries, overheads and profit go on once, to the whole bill. No VAT.
Still to buildRetentionWork done
Zadatak 4Monthly valuationWork done to date, less retention. VAT is added to what is paid.
Variation 01Contract sum
Zadatak 5VariationChanged work, valued at the bill's rates, moves the contract sum.

Plavo je ono što zadatak dodaje; sivo se prenosi od prije.

Ukratko. Rates stay net. Mark-ups go on once. VAT follows each payment.