Course introduction · 3 min

Tender to first valuation (UK, JCT)

You are the quantity surveyor for the main contractor. In five tasks you take a four-storey office from the priced bill to the first monthly payment and the first change.

Start task 1

The site: a four-storey concrete frame office under construction.Fictional project
Tallowgate WorksFour-storey office
Building
Four-storey office, shell and core
Contract
JCT SBC/Q 2024, with bills of quantities
Story
June to October 2026
Work in the ERP
5 tasks, about 1 h 45 min

Who hands what to whom

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Comes to you

  • EstimatorYour firm
    • Net ratesTask 1
  • Three dry lining firmsSubcontract bidders
    • BidsTask 3
  • ArchitectIssues instructions
    • InstructionTask 5
YouQuantity surveyor, main contractor

Goes from you

    • TenderTask 2
    • ValuationTask 4
    • VariationTask 5
    Client's QSFor the developer
    • OrderTask 3
    Dry lining subcontractorLowest complete bid

The project and the people are fictional. Portraits are generated.

Your route through the job

Two tasks at tender, one to buy the work, two on site. Each task you pass adds a line to your job file.

  1. At tender

    Task 1 · 15 min

    Price the dry lining package

    You produce
    The dry lining allowance
    Document
    Bill of quantities, dry lining lines
    In the ERP
    Bill of Quantities
  2. At tender

    Task 2 · 20 min

    Build the tender sum

    You produce
    The tender sum, without VAT
    Document
    Your firm's mark-ups on the bill
    In the ERP
    Bill of Quantities, Markups
  3. Buying the work

    Task 3 · 25 min

    Level the dry lining bids and award

    You produce
    The dry lining subcontract
    Document
    Levelled bids and the award decision
    In the ERP
    Bid Management
  4. On site

    Task 4 · 20 min

    Interim Valuation 1 (September)

    You produce
    Interim Valuation 1 and its VAT
    Document
    Progress claim for September
    In the ERP
    Contracts, Progress Claims
  5. On site

    Task 5 · 25 min

    Value Variation 01 (AI 07)

    You produce
    Variation 01 and the new contract sum
    Document
    Architect's Instruction AI 07
    In the ERP
    Variations

How a rate becomes a payment

Each step below is one task, in the order the money moves. Task 3, buying the dry lining, sits between the tender sum and the first valuation.

Bill lines at net rates
Task 1Direct costQuantity times net rate, line by line. Cost only.
Overheads and profitPreliminariesDirect cost
Task 2Tender sumPreliminaries, overheads and profit go on once, to the whole bill. No VAT.
Still to buildRetentionWork done
Task 4Monthly valuationWork done to date, less retention. VAT is added to what is paid.
Variation 01Contract sum
Task 5VariationChanged work, valued at the bill's rates, moves the contract sum.

Blue is what the task adds; grey is carried over from before.

In short. Rates stay net. Mark-ups go on once. VAT follows each payment.