Course introduction · 3 min
Tender to first valuation (UK, JCT)
You are the quantity surveyor for the main contractor. In five tasks you take a four-storey office from the priced bill to the first monthly payment and the first change.
Fictional project- Building
- Four-storey office, shell and core
- Contract
- JCT SBC/Q 2024, with bills of quantities
- Story
- June to October 2026
- Work in the ERP
- 5 tasks, about 1 h 45 min
Who hands what to whom
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Comes to you
EstimatorYour firm- Net ratesTask 1
Three dry lining firmsSubcontract bidders- BidsTask 3
- ArchitectIssues instructions
- InstructionTask 5
YouQuantity surveyor, main contractorGoes from you
- TenderTask 2
- ValuationTask 4
- VariationTask 5
Client's QSFor the developer- OrderTask 3
The project and the people are fictional. Portraits are generated.
Your route through the job
Two tasks at tender, one to buy the work, two on site. Each task you pass adds a line to your job file.
At tender
Task 1 · 15 min
Price the dry lining package
- You produce
- The dry lining allowance
- Document
- Bill of quantities, dry lining lines
- In the ERP
- Bill of Quantities
At tender
Task 2 · 20 min
Build the tender sum
- You produce
- The tender sum, without VAT
- Document
- Your firm's mark-ups on the bill
- In the ERP
- Bill of Quantities, Markups
Buying the work
Task 3 · 25 min
Level the dry lining bids and award
- You produce
- The dry lining subcontract
- Document
- Levelled bids and the award decision
- In the ERP
- Bid Management
On site
Task 4 · 20 min
Interim Valuation 1 (September)
- You produce
- Interim Valuation 1 and its VAT
- Document
- Progress claim for September
- In the ERP
- Contracts, Progress Claims
On site
Task 5 · 25 min
Value Variation 01 (AI 07)
- You produce
- Variation 01 and the new contract sum
- Document
- Architect's Instruction AI 07
- In the ERP
- Variations
How a rate becomes a payment
Each step below is one task, in the order the money moves. Task 3, buying the dry lining, sits between the tender sum and the first valuation.
Blue is what the task adds; grey is carried over from before.
In short. Rates stay net. Mark-ups go on once. VAT follows each payment.