Introduksjon til kurset · 3 min

Fra tilbud til første verdiberegning (Storbritannia, JCT)

You are the quantity surveyor for the main contractor. In five tasks you take a four-storey office from the priced bill to the first monthly payment and the first change.

Start oppgave 1

The site: a four-storey concrete frame office under construction.Fiktivt prosjekt
Tallowgate WorksFour-storey office
Building
Four-storey office, shell and core
Contract
JCT SBC/Q 2024, with bills of quantities
Story
June to October 2026
Arbeid i ERP
5 oppgaver, omtrent 1 t 45 min

Hvem gir hva til hvem

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Kommer til deg

  • EstimatorYour firm
    • Net ratesOppgave 1
  • Three dry lining firmsSubcontract bidders
    • BidsOppgave 3
  • ArchitectIssues instructions
    • InstructionOppgave 5
DuQuantity surveyor, main contractor

Går fra deg

    • TenderOppgave 2
    • ValuationOppgave 4
    • VariationOppgave 5
    Client's QSFor the developer
    • OrderOppgave 3
    Dry lining subcontractorLowest complete bid

Prosjektet og personene er fiktive. Portrettene er genererte.

Din vei gjennom prosjektet

Two tasks at tender, one to buy the work, two on site. Each task you pass adds a line to your job file.

  1. At tender

    Oppgave 1 · 15 min

    Prisfest gipspakken

    Du leverer
    The dry lining allowance
    Dokument
    Bill of quantities, dry lining lines
    I ERP
    Bill of Quantities
  2. At tender

    Oppgave 2 · 20 min

    Bygg tilbudssummen

    Du leverer
    The tender sum, without VAT
    Dokument
    Your firm's mark-ups on the bill
    I ERP
    Bill of Quantities, Markups
  3. Buying the work

    Oppgave 3 · 25 min

    Utjevn gipstilbudene og tildel

    Du leverer
    The dry lining subcontract
    Dokument
    Levelled bids and the award decision
    I ERP
    Bid Management
  4. On site

    Oppgave 4 · 20 min

    Interim Valuation 1 (september)

    Du leverer
    Interim Valuation 1 and its VAT
    Dokument
    Progress claim for September
    I ERP
    Contracts, Progress Claims
  5. On site

    Oppgave 5 · 25 min

    Verdiberegn Variation 01 (AI 07)

    Du leverer
    Variation 01 and the new contract sum
    Dokument
    Architect's Instruction AI 07
    I ERP
    Variations

How a rate becomes a payment

Each step below is one task, in the order the money moves. Task 3, buying the dry lining, sits between the tender sum and the first valuation.

Bill lines at net rates
Oppgave 1Direct costQuantity times net rate, line by line. Cost only.
Overheads and profitPreliminariesDirect cost
Oppgave 2Tender sumPreliminaries, overheads and profit go on once, to the whole bill. No VAT.
Still to buildRetentionWork done
Oppgave 4Monthly valuationWork done to date, less retention. VAT is added to what is paid.
Variation 01Contract sum
Oppgave 5VariationChanged work, valued at the bill's rates, moves the contract sum.

Blått er det oppgaven legger til; grått er overført fra før.

Kort sagt. Rates stay net. Mark-ups go on once. VAT follows each payment.