Kursuse sissejuhatus · 3 min

Pakkumisest esimese vahehindamiseni (Ühendkuningriik, JCT)

You are the quantity surveyor for the main contractor. In five tasks you take a four-storey office from the priced bill to the first monthly payment and the first change.

Alusta ülesannet 1

The site: a four-storey concrete frame office under construction.Väljamõeldud projekt
Tallowgate WorksFour-storey office
Building
Four-storey office, shell and core
Contract
JCT SBC/Q 2024, with bills of quantities
Story
June to October 2026
Töö ERP-s
Ülesandeid 5, umbes 1 h 45 min

Kes annab kellele mida

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Tuleb sinule

  • EstimatorYour firm
    • Net ratesÜlesanne 1
  • Three dry lining firmsSubcontract bidders
    • BidsÜlesanne 3
  • ArchitectIssues instructions
    • InstructionÜlesanne 5
SinaQuantity surveyor, main contractor

Läheb sinult

    • TenderÜlesanne 2
    • ValuationÜlesanne 4
    • VariationÜlesanne 5
    Client's QSFor the developer
    • OrderÜlesanne 3
    Dry lining subcontractorLowest complete bid

Projekt ja inimesed on väljamõeldud. Portreed on genereeritud.

Sinu tee läbi projekti

Two tasks at tender, one to buy the work, two on site. Each task you pass adds a line to your job file.

  1. At tender

    Ülesanne 1 · 15 min

    Hinnastage kipsplaattööde pakett

    Sinu tulemus
    The dry lining allowance
    Dokument
    Bill of quantities, dry lining lines
    ERP-s
    Bill of Quantities
  2. At tender

    Ülesanne 2 · 20 min

    Koostage pakkumuse summa

    Sinu tulemus
    The tender sum, without VAT
    Dokument
    Your firm's mark-ups on the bill
    ERP-s
    Bill of Quantities, Markups
  3. Buying the work

    Ülesanne 3 · 25 min

    Viige kipsplaattööde pakkumused võrreldavaks ja andke tellimus

    Sinu tulemus
    The dry lining subcontract
    Dokument
    Levelled bids and the award decision
    ERP-s
    Bid Management
  4. On site

    Ülesanne 4 · 20 min

    Vahehindamine 1 (september)

    Sinu tulemus
    Interim Valuation 1 and its VAT
    Dokument
    Progress claim for September
    ERP-s
    Contracts, Progress Claims
  5. On site

    Ülesanne 5 · 25 min

    Hinnake muudatus 01 (AI 07)

    Sinu tulemus
    Variation 01 and the new contract sum
    Dokument
    Architect's Instruction AI 07
    ERP-s
    Variations

How a rate becomes a payment

Each step below is one task, in the order the money moves. Task 3, buying the dry lining, sits between the tender sum and the first valuation.

Bill lines at net rates
Ülesanne 1Direct costQuantity times net rate, line by line. Cost only.
Overheads and profitPreliminariesDirect cost
Ülesanne 2Tender sumPreliminaries, overheads and profit go on once, to the whole bill. No VAT.
Still to buildRetentionWork done
Ülesanne 4Monthly valuationWork done to date, less retention. VAT is added to what is paid.
Variation 01Contract sum
Ülesanne 5VariationChanged work, valued at the bill's rates, moves the contract sum.

Sinine on see, mida ülesanne lisab; hall tuleb varasemast.

Lühidalt. Rates stay net. Mark-ups go on once. VAT follows each payment.