Kursuse sissejuhatus · 3 min
Pakkumisest esimese vahehindamiseni (Ühendkuningriik, JCT)
You are the quantity surveyor for the main contractor. In five tasks you take a four-storey office from the priced bill to the first monthly payment and the first change.
Väljamõeldud projekt- Building
- Four-storey office, shell and core
- Contract
- JCT SBC/Q 2024, with bills of quantities
- Story
- June to October 2026
- Töö ERP-s
- Ülesandeid 5, umbes 1 h 45 min
Kes annab kellele mida
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Tuleb sinule
EstimatorYour firm- Net ratesÜlesanne 1
Three dry lining firmsSubcontract bidders- BidsÜlesanne 3
- ArchitectIssues instructions
- InstructionÜlesanne 5
SinaQuantity surveyor, main contractorLäheb sinult
- TenderÜlesanne 2
- ValuationÜlesanne 4
- VariationÜlesanne 5
Client's QSFor the developer- OrderÜlesanne 3
Projekt ja inimesed on väljamõeldud. Portreed on genereeritud.
Sinu tee läbi projekti
Two tasks at tender, one to buy the work, two on site. Each task you pass adds a line to your job file.
At tender
Ülesanne 1 · 15 min
Hinnastage kipsplaattööde pakett
- Sinu tulemus
- The dry lining allowance
- Dokument
- Bill of quantities, dry lining lines
- ERP-s
- Bill of Quantities
At tender
Ülesanne 2 · 20 min
Koostage pakkumuse summa
- Sinu tulemus
- The tender sum, without VAT
- Dokument
- Your firm's mark-ups on the bill
- ERP-s
- Bill of Quantities, Markups
Buying the work
Ülesanne 3 · 25 min
Viige kipsplaattööde pakkumused võrreldavaks ja andke tellimus
- Sinu tulemus
- The dry lining subcontract
- Dokument
- Levelled bids and the award decision
- ERP-s
- Bid Management
On site
Ülesanne 4 · 20 min
Vahehindamine 1 (september)
- Sinu tulemus
- Interim Valuation 1 and its VAT
- Dokument
- Progress claim for September
- ERP-s
- Contracts, Progress Claims
On site
Ülesanne 5 · 25 min
Hinnake muudatus 01 (AI 07)
- Sinu tulemus
- Variation 01 and the new contract sum
- Dokument
- Architect's Instruction AI 07
- ERP-s
- Variations
How a rate becomes a payment
Each step below is one task, in the order the money moves. Task 3, buying the dry lining, sits between the tender sum and the first valuation.
Sinine on see, mida ülesanne lisab; hall tuleb varasemast.
Lühidalt. Rates stay net. Mark-ups go on once. VAT follows each payment.