Introduktion til kurset · 3 min
Fra tilbud til første acontoopgørelse (Storbritannien, JCT)
You are the quantity surveyor for the main contractor. In five tasks you take a four-storey office from the priced bill to the first monthly payment and the first change.
Fiktivt projekt- Building
- Four-storey office, shell and core
- Contract
- JCT SBC/Q 2024, with bills of quantities
- Story
- June to October 2026
- Arbejde i ERP
- 5 opgaver, cirka 1 t 45 min
Hvem giver hvad til hvem
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Kommer til dig
EstimatorYour firm- Net ratesOpgave 1
Three dry lining firmsSubcontract bidders- BidsOpgave 3
- ArchitectIssues instructions
- InstructionOpgave 5
DigQuantity surveyor, main contractorGår fra dig
- TenderOpgave 2
- ValuationOpgave 4
- VariationOpgave 5
Client's QSFor the developer- OrderOpgave 3
Projektet og personerne er fiktive. Portrætterne er genererede.
Din vej gennem sagen
Two tasks at tender, one to buy the work, two on site. Each task you pass adds a line to your job file.
At tender
Opgave 1 · 15 min
Prissæt pakken med indvendige gipsvægge
- Du leverer
- The dry lining allowance
- Dokument
- Bill of quantities, dry lining lines
- I ERP
- Bill of Quantities
At tender
Opgave 2 · 20 min
Opbyg tilbudssummen
- Du leverer
- The tender sum, without VAT
- Dokument
- Your firm's mark-ups on the bill
- I ERP
- Bill of Quantities, Markups
Buying the work
Opgave 3 · 25 min
Normalisér gipstilbuddene og tildel
- Du leverer
- The dry lining subcontract
- Dokument
- Levelled bids and the award decision
- I ERP
- Bid Management
On site
Opgave 4 · 20 min
Acontoopgørelse 1 (september)
- Du leverer
- Interim Valuation 1 and its VAT
- Dokument
- Progress claim for September
- I ERP
- Contracts, Progress Claims
On site
Opgave 5 · 25 min
Opgør ændringsordre 01 (AI 07)
- Du leverer
- Variation 01 and the new contract sum
- Dokument
- Architect's Instruction AI 07
- I ERP
- Variations
How a rate becomes a payment
Each step below is one task, in the order the money moves. Task 3, buying the dry lining, sits between the tender sum and the first valuation.
Blå er det, opgaven tilføjer; grå er overført fra før.
Kort sagt. Rates stay net. Mark-ups go on once. VAT follows each payment.