Fra tilbud til første acontoopgørelse (Storbritannien, JCT)

You are the quantity surveyor for the main contractor. In five tasks you take a four-storey office from the priced bill to the first monthly payment and the first change.

Start opgave 1

The site: a four-storey concrete frame office under construction.Fiktivt projekt
Tallowgate WorksFour-storey office
Building
Four-storey office, shell and core
Contract
JCT SBC/Q 2024, with bills of quantities
Story
June to October 2026
Arbejde i ERP
5 opgaver, cirka 1 t 45 min

Hvem giver hvad til hvem

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Kommer til dig

  • EstimatorYour firm
    • Net ratesOpgave 1
  • Three dry lining firmsSubcontract bidders
    • BidsOpgave 3
  • ArchitectIssues instructions
    • InstructionOpgave 5
DigQuantity surveyor, main contractor

Går fra dig

    • TenderOpgave 2
    • ValuationOpgave 4
    • VariationOpgave 5
    Client's QSFor the developer
    • OrderOpgave 3
    Dry lining subcontractorLowest complete bid

Projektet og personerne er fiktive. Portrætterne er genererede.

Din vej gennem sagen

Two tasks at tender, one to buy the work, two on site. Each task you pass adds a line to your job file.

  1. At tender

    Opgave 1 · 15 min

    Prissæt pakken med indvendige gipsvægge

    Du leverer
    The dry lining allowance
    Dokument
    Bill of quantities, dry lining lines
    I ERP
    Bill of Quantities
  2. At tender

    Opgave 2 · 20 min

    Opbyg tilbudssummen

    Du leverer
    The tender sum, without VAT
    Dokument
    Your firm's mark-ups on the bill
    I ERP
    Bill of Quantities, Markups
  3. Buying the work

    Opgave 3 · 25 min

    Normalisér gipstilbuddene og tildel

    Du leverer
    The dry lining subcontract
    Dokument
    Levelled bids and the award decision
    I ERP
    Bid Management
  4. On site

    Opgave 4 · 20 min

    Acontoopgørelse 1 (september)

    Du leverer
    Interim Valuation 1 and its VAT
    Dokument
    Progress claim for September
    I ERP
    Contracts, Progress Claims
  5. On site

    Opgave 5 · 25 min

    Opgør ændringsordre 01 (AI 07)

    Du leverer
    Variation 01 and the new contract sum
    Dokument
    Architect's Instruction AI 07
    I ERP
    Variations

How a rate becomes a payment

Each step below is one task, in the order the money moves. Task 3, buying the dry lining, sits between the tender sum and the first valuation.

Bill lines at net rates
Opgave 1Direct costQuantity times net rate, line by line. Cost only.
Overheads and profitPreliminariesDirect cost
Opgave 2Tender sumPreliminaries, overheads and profit go on once, to the whole bill. No VAT.
Still to buildRetentionWork done
Opgave 4Monthly valuationWork done to date, less retention. VAT is added to what is paid.
Variation 01Contract sum
Opgave 5VariationChanged work, valued at the bill's rates, moves the contract sum.

Blå er det, opgaven tilføjer; grå er overført fra før.

Kort sagt. Rates stay net. Mark-ups go on once. VAT follows each payment.