Inleiding tot de cursus · 3 min
Van aanbieding tot eerste waardering (VK, JCT)
You are the quantity surveyor for the main contractor. In five tasks you take a four-storey office from the priced bill to the first monthly payment and the first change.
Fictief project- Building
- Four-storey office, shell and core
- Contract
- JCT SBC/Q 2024, with bills of quantities
- Story
- June to October 2026
- Werk in de ERP
- 5 opdrachten, ongeveer 1 u 45 min
Wie geeft wat aan wie
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Komt bij u
EstimatorYour firm- Net ratesOpdracht 1
Three dry lining firmsSubcontract bidders- BidsOpdracht 3
- ArchitectIssues instructions
- InstructionOpdracht 5
UQuantity surveyor, main contractorGaat van u uit
- TenderOpdracht 2
- ValuationOpdracht 4
- VariationOpdracht 5
Client's QSFor the developer- OrderOpdracht 3
Het project en de mensen zijn fictief. De portretten zijn gegenereerd.
Uw route door het project
Two tasks at tender, one to buy the work, two on site. Each task you pass adds a line to your job file.
At tender
Opdracht 1 · 15 min
Prijs het pakket droogbouw
- U levert
- The dry lining allowance
- Document
- Bill of quantities, dry lining lines
- In de ERP
- Bill of Quantities
At tender
Opdracht 2 · 20 min
Bouw de aanbiedingssom op
- U levert
- The tender sum, without VAT
- Document
- Your firm's mark-ups on the bill
- In de ERP
- Bill of Quantities, Markups
Buying the work
Opdracht 3 · 25 min
Nivelleer de droogbouwinschrijvingen en gun
- U levert
- The dry lining subcontract
- Document
- Levelled bids and the award decision
- In de ERP
- Bid Management
On site
Opdracht 4 · 20 min
Interim Valuation 1 (september)
- U levert
- Interim Valuation 1 and its VAT
- Document
- Progress claim for September
- In de ERP
- Contracts, Progress Claims
On site
Opdracht 5 · 25 min
Waardeer meerwerk 01 (AI 07)
- U levert
- Variation 01 and the new contract sum
- Document
- Architect's Instruction AI 07
- In de ERP
- Variations
How a rate becomes a payment
Each step below is one task, in the order the money moves. Task 3, buying the dry lining, sits between the tender sum and the first valuation.
Blauw is wat de opdracht toevoegt; grijs komt uit de stap ervoor.
Kort gezegd. Rates stay net. Mark-ups go on once. VAT follows each payment.