Cheat sheet
AI-generated programme, verified (Brazil)
Every rule of the course on one page: how each figure is built, the mistake people usually make, and where it comes up at work. Print it or keep it open while you work.
- Rule
- Duration = quantity × tradesman's coefficient ÷ (tradesmen × 8 h), rounded up. The labourer does not set the pace.
- How it is built
- Hours of the task = Quantity × Tradesman coefficient
- Duration = Hours of the task ÷ (Tradesmen × hours per day) + Rounding up
- Usual mistake
- The bricklayer's hours are right. Divide them by the 4 bricklayers only.
- At work
- The planner takes durations from the cost composições (build-ups) and checks productivity with the foreman.
- Rule
- Duration = quantity × tradesman's coefficient ÷ (tradesmen × 8 h), rounded up. The labourer does not set the pace.
- How it is built
- Hours of the task = Quantity × Tradesman coefficient
- Duration = Hours of the task ÷ (Tradesmen × hours per day) + Rounding up
- Usual mistake
- The bricklayer's hours are right. The labourers do not enter the division.
- At work
- The planner builds the whole network before discussing the term: no date can be checked without every activity.
- Rule
- Every link needs a construction reason. A link with no reason eats float and lengthens the programme.
- How it is built
- Days gained = Draft duration − Corrected duration
- Total float = Late start − Early start
- Usual mistake
- The draft length is read right. The days gained are that length less the corrected one.
- At work
- In the schedule review, the client's supervisor asks the reason for each link on the critical path.
- Rule
- The planned length is the longest path, in working days. The contract end date counts calendar days.
- How it is built
- Planned length = Early finish of the last activity, in working days
- Margin = Contract end date − Planned finish, in calendar days
- Usual mistake
- Both periods are right. Compare dates, not day counts from different calendars.
- At work
- At each measurement, the engineer checks the planned finish against the end date of the start order.
- Rule
- Physical progress = earned value ÷ contract value. Elapsed time measures the plan, not the works.
- How it is built
- Planned value = Activity value × elapsed days ÷ duration, summed
- Physical progress = Earned value ÷ Contract value
- Usual mistake
- The period is right. Physical progress comes from the measurement, not the calendar.
- At work
- Every month the measurement feeds the earned value, and the schedule index goes into the report to the client.
- Rule
- The S-curve adds up planned value; cash shifts the income by a month. The lowest point is the working capital.
- How it is built
- S-curve = Cumulative planned value ÷ Contract value
- Cost of the month = Value of the month ÷ (1 + BDI)
- Cumulative balance = Inflows to the month − Outflows to the month
- Usual mistake
- The costs are right. Each month's measurement comes in the month after.
- At work
- The contractor's finance team uses the physical-financial schedule to forecast the project's working capital.