Cheat sheet

AI-generated programme, verified (Brazil)

Every rule of the course on one page: how each figure is built, the mistake people usually make, and where it comes up at work. Print it or keep it open while you work.

Task 1

The blockwork duration from the composição

Theory (8 min)
Rule
Duration = quantity × tradesman's coefficient ÷ (tradesmen × 8 h), rounded up. The labourer does not set the pace.
How it is built
  • Hours of the task = Quantity × Tradesman coefficient
  • Duration = Hours of the task ÷ (Tradesmen × hours per day) + Rounding up
Usual mistake
The bricklayer's hours are right. Divide them by the 4 bricklayers only.
At work
The planner takes durations from the cost composições (build-ups) and checks productivity with the foreman.

Task 2

The full programme: render, painting and the draft's logic

Theory (8 min)
Rule
Duration = quantity × tradesman's coefficient ÷ (tradesmen × 8 h), rounded up. The labourer does not set the pace.
How it is built
  • Hours of the task = Quantity × Tradesman coefficient
  • Duration = Hours of the task ÷ (Tradesmen × hours per day) + Rounding up
Usual mistake
The bricklayer's hours are right. The labourers do not enter the division.
At work
The planner builds the whole network before discussing the term: no date can be checked without every activity.

Task 3

Invented links: the logic the AI made up

Theory (8 min)
Rule
Every link needs a construction reason. A link with no reason eats float and lengthens the programme.
How it is built
  • Days gained = Draft duration − Corrected duration
  • Total float = Late start − Early start
Usual mistake
The draft length is read right. The days gained are that length less the corrected one.
At work
In the schedule review, the client's supervisor asks the reason for each link on the critical path.

Task 4

Critical path and finish: does it fit the period?

Theory (8 min)
Rule
The planned length is the longest path, in working days. The contract end date counts calendar days.
How it is built
  • Planned length = Early finish of the last activity, in working days
  • Margin = Contract end date − Planned finish, in calendar days
Usual mistake
Both periods are right. Compare dates, not day counts from different calendars.
At work
At each measurement, the engineer checks the planned finish against the end date of the start order.

Task 5

Physical progress: measured, not assumed

Theory (8 min)
Rule
Physical progress = earned value ÷ contract value. Elapsed time measures the plan, not the works.
How it is built
  • Planned value = Activity value × elapsed days ÷ duration, summed
  • Physical progress = Earned value ÷ Contract value
Usual mistake
The period is right. Physical progress comes from the measurement, not the calendar.
At work
Every month the measurement feeds the earned value, and the schedule index goes into the report to the client.

Task 6

S-curve and cash: the physical-financial programme

Theory (8 min)
Rule
The S-curve adds up planned value; cash shifts the income by a month. The lowest point is the working capital.
How it is built
  • S-curve = Cumulative planned value ÷ Contract value
  • Cost of the month = Value of the month ÷ (1 + BDI)
  • Cumulative balance = Inflows to the month − Outflows to the month
Usual mistake
The costs are right. Each month's measurement comes in the month after.
At work
The contractor's finance team uses the physical-financial schedule to forecast the project's working capital.

Back to the course