Cheat sheet

AI-drafted progress claims, verified (France)

Every rule of the course on one page: how each figure is built, the mistake people usually make, and where it comes up at work. Print it or keep it open while you work.

Task 1

The April situation: measured quantity × BPU price

Theory (9 min)
Rule
Situation = measured quantity × BPU price, line by line. Only the quantity fixed and measured is paid.
How it is built
  • Month's works, by line = Cumulative to the end of May − Cumulative to the end of April
At work
Each month the site manager builds the situation from the measured quantities and checks it before sending it to the project manager (maître d'œuvre).

Task 2

Progress line by line: what the AI billed

Theory (9 min)
Rule
Gap = draft − verified, line by line, with its sign. A line that is too low reduces the total gap.
How it is built
  • Difference = AI draft total − May works read in the ERP
Usual mistake
All three lines are found. On 04.6 the draft is lower: that gap comes off.
At work
Before it goes out, the cost manager matches each line of the draft situation to the signed measurement.

Task 3

The BT01 revision: the month the contract names

Theory (9 min)
Rule
Base month: the offer. Index: m − 2. Cn up to the thousandth. The revision covers the month's work.
How it is built
  • Cn = Fixed part + Variable part × BT01(m − 2) ÷ BT01(0) + Rounded up to the next thousandth
  • Revision = Month's works excl. VAT × (Cn − 1)
Usual mistake
The base month is right. The contract takes m − 2: March's index.
At work
The company calculates the revision of each situation with the latest published BT index, using the CCAP formula.

Task 4

Retention: 5 % of the revised payment with VAT

Theory (7 min)
Rule
5 % of the payment with VAT, revision included. The SME 3 % applies only to the State and buyers above 60 M€.
How it is built
  • Base = (Month's works + revision) × 1,20
  • Retention = Contract rate × Base
Usual mistake
Work and revision are right. The contract takes the amount with VAT: add it.
At work
The project manager (maître d'œuvre) checks the retention base on each interim payment; a wrong base is corrected in the final account.

Task 5

The advance: repaid once, from the right threshold

Theory (8 min)
Rule
Nothing below 65 %, all by 80 %, straight-line between. The advance is repaid only once.
How it is built
  • Ratio = Cumulative work done excl. VAT ÷ Initial amount excl. VAT
  • Portion crossed = (Ratio − 65 %) ÷ 15 %
  • Recoupment = Advance × Portion crossed
Usual mistake
The 65 % threshold is passed. The contract spreads repayment to 80 %.
At work
The public accountant recoups the advance from each interim payment as soon as the threshold is passed; the company checks the calculation.

Task 6

The invoice and the amount payable

Theory (8 min)
Rule
The contractor invoices the commune with VAT. Reverse charge is for the subcontractor; the deduction comes off after VAT.
How it is built
  • Interim payment incl. VAT = (Invoice excl. VAT + revision) × 1,20
  • Amount payable = Interim payment incl. VAT − Retention − Advance deduction
Usual mistake
Retention and deduction are right. The contractor invoices the commune with VAT.
At work
Each certified situation goes out as an invoice on Chorus Pro; the accountant pays the net amount after retention and recoupment.