Cheat sheet
AI-drafted progress claims, verified (France)
Every rule of the course on one page: how each figure is built, the mistake people usually make, and where it comes up at work. Print it or keep it open while you work.
- Rule
- Situation = measured quantity × BPU price, line by line. Only the quantity fixed and measured is paid.
- How it is built
- Month's works, by line = Cumulative to the end of May − Cumulative to the end of April
- At work
- Each month the site manager builds the situation from the measured quantities and checks it before sending it to the project manager (maître d'œuvre).
- Rule
- Gap = draft − verified, line by line, with its sign. A line that is too low reduces the total gap.
- How it is built
- Difference = AI draft total − May works read in the ERP
- Usual mistake
- All three lines are found. On 04.6 the draft is lower: that gap comes off.
- At work
- Before it goes out, the cost manager matches each line of the draft situation to the signed measurement.
- Rule
- Base month: the offer. Index: m − 2. Cn up to the thousandth. The revision covers the month's work.
- How it is built
- Cn = Fixed part + Variable part × BT01(m − 2) ÷ BT01(0) + Rounded up to the next thousandth
- Revision = Month's works excl. VAT × (Cn − 1)
- Usual mistake
- The base month is right. The contract takes m − 2: March's index.
- At work
- The company calculates the revision of each situation with the latest published BT index, using the CCAP formula.
- Rule
- 5 % of the payment with VAT, revision included. The SME 3 % applies only to the State and buyers above 60 M€.
- How it is built
- Base = (Month's works + revision) × 1,20
- Retention = Contract rate × Base
- Usual mistake
- Work and revision are right. The contract takes the amount with VAT: add it.
- At work
- The project manager (maître d'œuvre) checks the retention base on each interim payment; a wrong base is corrected in the final account.
- Rule
- Nothing below 65 %, all by 80 %, straight-line between. The advance is repaid only once.
- How it is built
- Ratio = Cumulative work done excl. VAT ÷ Initial amount excl. VAT
- Portion crossed = (Ratio − 65 %) ÷ 15 %
- Recoupment = Advance × Portion crossed
- Usual mistake
- The 65 % threshold is passed. The contract spreads repayment to 80 %.
- At work
- The public accountant recoups the advance from each interim payment as soon as the threshold is passed; the company checks the calculation.
- Rule
- The contractor invoices the commune with VAT. Reverse charge is for the subcontractor; the deduction comes off after VAT.
- How it is built
- Interim payment incl. VAT = (Invoice excl. VAT + revision) × 1,20
- Amount payable = Interim payment incl. VAT − Retention − Advance deduction
- Usual mistake
- Retention and deduction are right. The contractor invoices the commune with VAT.
- At work
- Each certified situation goes out as an invoice on Chorus Pro; the accountant pays the net amount after retention and recoupment.