Cheat sheet

Document control in a CDE (UK)

Every rule of the course on one page: how each figure is built, the mistake people usually make, and where it comes up at work. Print it or keep it open while you work.

Task 1

Steel cut from an S2 drawing

Theory (7 min)
Rule
On the register is not the same as authorised. Read the state and the code before anyone cuts, orders or builds.
How it is built
  • Steel at risk = Steel on S-2101 P02 + Steel on S-2103 P01
Usual mistake
Only the drawings on the register counted. S-2103 came by e-mail and is not authorised either.
At work
A document controller checks every cutting list, order and method statement against the register before it is released.

Task 2

Authorise and issue for construction

Theory (7 min)
Rule
Authorise, then transmit. The register says what may be built; the transmittal proves who got it and when.
How it is built
  • Working days = Days 26 Mar to 2 Apr − Weekend − Bank holidays
Usual mistake
Good Friday and Easter Monday counted as working days. Both are bank holidays.
At work
The controller publishes the construction revision, issues it by transmittal the same day and flags any tight lead time.

Task 3

Every holder of P02 gets C01

Theory (6 min)
Rule
A superseded drawing is only dead when nobody holds it. Send the new revision to every holder of the old one.
How it is built
  • Still on P02 = P02 holders − Sent C01 in task 2
Usual mistake
The originator counted. The engineer wrote C01; they are not on P02.
At work
Each new revision goes out against the old distribution list, and the controller records who has the current one.

Task 4

File names that break the standard

Theory (6 min)
Rule
A name is data. Check it field by field; return a bad one to its originator instead of fixing it quietly.
How it is built
  • Returned = Names submitted − Names that pass
Usual mistake
One fault missed. Check every field: one name breaks the level, another the type.
At work
Submissions are checked against the information standard on arrival; failures go back to the originator with the field named.