Cheat sheet
Final account (UK, NEC4 Option B)
Every rule of the course on one page: how each figure is built, the mistake people usually make, and where it comes up at work. Print it or keep it open while you work.
- Rule
- Agreed, not asked. The Prices move by the agreed value of an implemented event, never by a quotation.
- How it is built
- Prices after the implemented events = Prices at the Contract Date + CE-01 + CE-02 agreed + CE-04 agreed
- Usual mistake
- You added CE-05 and CE-08 as quoted. A quotation changes the Prices only once it is accepted or assessed.
- At work
- The commercial manager reconciles the register with the Project Manager's letters before every cost report.
- Rule
- Defined Cost of the event plus the Fee. What would have happened anyway is not the event's cost.
- How it is built
- CE-05 as assessed = Own cost + Roofer standing + One scaffold week + Fee
- Disputed balance = Quotation − CE-05 agreed
- Usual mistake
- You put 10 % on everything. Subcontracted cost carries the lower 5 % Fee.
- At work
- The commercial manager records the assessment at once and keeps the disputed parts on a separate list.
- Rule
- Silence plus notice plus two weeks. A quotation is never accepted by silence alone.
- How it is built
- Days to acceptance = Notice date + 14 days − Quotation date
- Usual mistake
- Two plus two weeks assumes the notice was sent the day the reply was due. It was sent two days later.
- At work
- A commercial team diaries every reply date and sends the failure notice the day after it passes.
- Rule
- Pay each square metre once. Remeasure the bill around the compensation events, not through them.
- How it is built
- Remeasurement adjustment = EW1 change + FL1 change + FL2 change
- Usual mistake
- The as-built FL1 and FL2 still hold the CE-01 rooms. That pays the floor change twice.
- At work
- The quantity surveyor agrees the as-built measure with the Project Manager's team and marks every room a CE already paid.
- Rule
- Everything agreed, less everything paid. The final assessment releases the retention and charges the uncorrected Defect.
- How it is built
- Final total = Prices + Events agreed + Remeasurement
- Amount due = Final total − Paid to date − Defect D-08
- Usual mistake
- You took the retention off again. In this assessment the rest of it is released.
- At work
- The commercial manager prepares the account before the certificate so the four-week window is not lost.