Cheat sheet

Final account (UK, NEC4 Option B)

Every rule of the course on one page: how each figure is built, the mistake people usually make, and where it comes up at work. Print it or keep it open while you work.

Task 1

What is agreed: the CE register at Completion

Theory (7 min)
Rule
Agreed, not asked. The Prices move by the agreed value of an implemented event, never by a quotation.
How it is built
  • Prices after the implemented events = Prices at the Contract Date + CE-01 + CE-02 agreed + CE-04 agreed
Usual mistake
You added CE-05 and CE-08 as quoted. A quotation changes the Prices only once it is accepted or assessed.
At work
The commercial manager reconciles the register with the Project Manager's letters before every cost report.

Task 2

The Project Manager's own assessment of CE-05

Theory (8 min)
Rule
Defined Cost of the event plus the Fee. What would have happened anyway is not the event's cost.
How it is built
  • CE-05 as assessed = Own cost + Roofer standing + One scaffold week + Fee
  • Disputed balance = Quotation − CE-05 agreed
Usual mistake
You put 10 % on everything. Subcontracted cost carries the lower 5 % Fee.
At work
The commercial manager records the assessment at once and keeps the disputed parts on a separate list.

Task 3

CE-08: a quotation nobody answered

Theory (6 min)
Rule
Silence plus notice plus two weeks. A quotation is never accepted by silence alone.
How it is built
  • Days to acceptance = Notice date + 14 days − Quotation date
Usual mistake
Two plus two weeks assumes the notice was sent the day the reply was due. It was sent two days later.
At work
A commercial team diaries every reply date and sends the failure notice the day after it passes.

Task 4

Remeasurement under Option B

Theory (8 min)
Rule
Pay each square metre once. Remeasure the bill around the compensation events, not through them.
How it is built
  • Remeasurement adjustment = EW1 change + FL1 change + FL2 change
Usual mistake
The as-built FL1 and FL2 still hold the CE-01 rooms. That pays the floor change twice.
At work
The quantity surveyor agrees the as-built measure with the Project Manager's team and marks every room a CE already paid.

Task 5

The final assessment

Theory (9 min)
Rule
Everything agreed, less everything paid. The final assessment releases the retention and charges the uncorrected Defect.
How it is built
  • Final total = Prices + Events agreed + Remeasurement
  • Amount due = Final total − Paid to date − Defect D-08
Usual mistake
You took the retention off again. In this assessment the rest of it is released.
At work
The commercial manager prepares the account before the certificate so the four-week window is not lost.