Cheat sheet

Bid leveling: drywall subcontractor bids (US)

Every rule of the course on one page: how each figure is built, the mistake people usually make, and where it comes up at work. Print it or keep it open while you work.

Task 1

The 1:05 phone bid: record it as quoted

Theory (8 min)
Rule
Record what the sub quoted, line by line. A blank stays blank.
How it is built
  • Brisco bid as recorded = DW-01 + DW-02 + DW-03 + DW-04
Usual mistake
You filled Brisco's blank DW-05 with Orvella's price. Record only what Brisco quoted; gaps are leveled on your sheet in task 2.
At work
In the last hour before a bid closes, estimators take sub prices by phone and record each one line by line.

Task 2

Open the bids and plug the gap

Theory (9 min)
Rule
Plug the gap on your sheet, at the highest price another bidder carried. Same scope for every bid.
How it is built
  • Talmadge leveled = DW-01, DW-02, DW-04 as bid + DW-03 plug
Usual mistake
You plugged DW-03 with the lowest other price. The rule is the highest: a plug stands in for a price nobody confirmed.
At work
Every bid-day leveling sheet has a plug column: the estimator's price for scope a sub left out.

Task 3

The leveled low, not the machine's rank

Theory (9 min)
Rule
Rank on the same scope, not on totals as bid. Award the leveled low at its leveled price.
How it is built
  • Awarded amount = Orvella raw total in leveling − DW-05 priced by Orvella
Usual mistake
You awarded the ERP's rank 1 on totals as bid. Take DW-05 off Orvella and compare the same four lines: Orvella is lower.
At work
The chief estimator signs the drywall carry only after the leveling sheet shows every bid on one scope.

Task 4

Carry the number and list your subs

Theory (9 min)
Rule
List every sub above one-half of 1 percent of the total bid. Own forces are not listed.
How it is built
  • Listing threshold = Total base bid × One-half of 1 percent
Usual mistake
You took the threshold on the direct cost. The rule says the total bid: the Grand Total, fee and bond included.
At work
Minutes before the deadline, the estimator fills the subcontractor list on the sealed bid form from the base bid.