Cheat sheet

Cost control at month 6: earned value and CVR

Every rule of the course on one page: how each figure is built, the mistake people usually make, and where it comes up at work. Print it or keep it open while you work.

Task 1

Budget at completion: cost, not the tender sum

Theory (8 min)
Rule
The baseline is the cost of the work. Mark-ups ride on top of it, so no index is ever measured against them.
How it is built
  • Budget at completion = Measured work + Preliminaries + Provisional sums
Usual mistake
That is the tender sum. The mark-ups have no work behind them; the baseline is the net cost.
At work
The cost engineer sets the baseline from the tender's net cost and changes it only through change control.

Task 2

Planned value at the month 6 data date

Theory (8 min)
Rule
Plan follows the programme, not the calendar. Each activity spends its budget over its own months.
How it is built
  • Planned value = Σ budget × months passed ÷ months long
Usual mistake
That is a straight line over 18 months. Follow the cost-loaded programme activity by activity.
At work
The planner and the quantity surveyor agree the cost loading before the first monthly report.

Task 3

Earned value and actual cost

Theory (9 min)
Rule
Earned value is a budget; actual cost is a cost of the same work. Accrue what was received; leave out what is only ordered.
How it is built
  • Earned value = Σ budget × measured %
  • Actual cost = Booked cost + Received, not invoiced
Usual mistake
That is the ledger as booked. Add what was received in October and not yet invoiced.
At work
Each month the site's measurement and the ledger meet here; the accrual list is agreed with accounts first.

Task 4

CPI, SPI and the outturn

Theory (9 min)
Rule
The method is part of the forecast. Set it before you read the outturn, and say which one the report uses.
How it is built
  • Variance at completion = Budget at completion − Outturn (EAC)
Usual mistake
Sign: VAC = BAC − EAC. An outturn above budget gives a negative variance.
At work
The monthly report states CPI, SPI and the outturn by the agreed method, with the others as the range.

Task 5

Cost-value reconciliation and the forecast margin

Theory (9 min)
Rule
Value is the work done at contract prices; cost includes what was received and not yet invoiced.
How it is built
  • Value to date = Σ earned value × mark-ups
  • Margin to date = Value to date − Cost to date − Accruals
  • Forecast margin = Tender sum − Outturn (EAC)
Usual mistake
That is the tender margin: tender sum less the budget. Use the outturn as the final cost.
At work
Contractors reconcile value and cost on every job each month; the board reviews it job by job.