Cheat sheet
Cost control at month 6: earned value and CVR
Every rule of the course on one page: how each figure is built, the mistake people usually make, and where it comes up at work. Print it or keep it open while you work.
- Rule
- The baseline is the cost of the work. Mark-ups ride on top of it, so no index is ever measured against them.
- How it is built
- Budget at completion = Measured work + Preliminaries + Provisional sums
- Usual mistake
- That is the tender sum. The mark-ups have no work behind them; the baseline is the net cost.
- At work
- The cost engineer sets the baseline from the tender's net cost and changes it only through change control.
- Rule
- Plan follows the programme, not the calendar. Each activity spends its budget over its own months.
- How it is built
- Planned value = Σ budget × months passed ÷ months long
- Usual mistake
- That is a straight line over 18 months. Follow the cost-loaded programme activity by activity.
- At work
- The planner and the quantity surveyor agree the cost loading before the first monthly report.
- Rule
- Earned value is a budget; actual cost is a cost of the same work. Accrue what was received; leave out what is only ordered.
- How it is built
- Earned value = Σ budget × measured %
- Actual cost = Booked cost + Received, not invoiced
- Usual mistake
- That is the ledger as booked. Add what was received in October and not yet invoiced.
- At work
- Each month the site's measurement and the ledger meet here; the accrual list is agreed with accounts first.
- Rule
- The method is part of the forecast. Set it before you read the outturn, and say which one the report uses.
- How it is built
- Variance at completion = Budget at completion − Outturn (EAC)
- Usual mistake
- Sign: VAC = BAC − EAC. An outturn above budget gives a negative variance.
- At work
- The monthly report states CPI, SPI and the outturn by the agreed method, with the others as the range.
- Rule
- Value is the work done at contract prices; cost includes what was received and not yet invoiced.
- How it is built
- Value to date = Σ earned value × mark-ups
- Margin to date = Value to date − Cost to date − Accruals
- Forecast margin = Tender sum − Outturn (EAC)
- Usual mistake
- That is the tender margin: tender sum less the budget. Use the outturn as the final cost.
- At work
- Contractors reconcile value and cost on every job each month; the board reviews it job by job.