Handover: O&M data, defects and retention release

Every rule of the course on one page: how each figure is built, the mistake people usually make, and where it comes up at work. Print it or keep it open while you work.

Task 1

O&M manuals before taking-over

Theory (7 min)
Rule
Delivered is not done. A required item counts only when its document is verified, or generated by a built package.
How it is built
  • Completeness = Verified slots ÷ Required slots × 100
Usual mistake
Returned documents are counted. Only verified items are delivered.
At work
In the last weeks before taking-over the package is reported weekly; the client's facility team asks what is accepted, not what arrived.

Task 2

Asset data against the client's requirements

Theory (8 min)
Rule
A row passes only if it meets every rule. One gap fails the row, and a repeated Name fails every row that uses it.
How it is built
  • Rows that pass = Component rows − Rows with a gap − Rows that share a Name
  • Compliance = Rows that pass ÷ Rows checked × 100
Usual mistake
The repeated Name is failed on one row only. Both rows that use it fail.
At work
Asset data is checked against the client's requirements before each handover drop, and failed rows go back to their author.

Task 3

Punch list before the Taking-Over Certificate

Theory (7 min)
Rule
Taking-over is not zero snags. Only an item that is a safety risk or stops the Works being used holds back the certificate.
How it is built
  • Items that prevent taking-over = Open punch items − Minor items listed in the TOC
Usual mistake
Every open item was counted. Minor items may be listed in the TOC and finished later.
At work
Before the Engineer's inspection the site team brings the punch list up to date and agrees what will be listed in the TOC.

Task 4

The Defects Notification Period register

Theory (9 min)
Rule
Late means after its own date. Each defect is measured against the date its notice or the TOC gave, not against the DNP expiry.
How it is built
  • DNP expiry = Date of completion + 365 days
  • Due date of a defect = Date notified, or the date of completion for TOC items + Days it was given
Usual mistake
You measured against the DNP expiry. Each defect has its own remedy date: D-03 and D-07 were late, and D-09 was not.
At work
The defects register is kept for the year after taking-over, and the client's team checks every remedy date against it.

Task 5

The two halves of the Retention Money

Theory (8 min)
Rule
Half at taking-over, the rest after the DNP, less what the Employer paid others to remedy.
How it is built
  • Retention released after the TOC = Limit of Retention Money ÷ 2
  • Net amount after the DNP = Second half − Engineer's figure for D-08
Usual mistake
That is all the Retention Money held. Only the first half is released after the Taking-Over Certificate.
At work
At taking-over and again at the end of the DNP the commercial team chases each half of the retention.