Cheat sheet
Handover: O&M data, defects and retention release
Every rule of the course on one page: how each figure is built, the mistake people usually make, and where it comes up at work. Print it or keep it open while you work.
- Rule
- Delivered is not done. A required item counts only when its document is verified, or generated by a built package.
- How it is built
- Completeness = Verified slots ÷ Required slots × 100
- Usual mistake
- Returned documents are counted. Only verified items are delivered.
- At work
- In the last weeks before taking-over the package is reported weekly; the client's facility team asks what is accepted, not what arrived.
- Rule
- A row passes only if it meets every rule. One gap fails the row, and a repeated Name fails every row that uses it.
- How it is built
- Rows that pass = Component rows − Rows with a gap − Rows that share a Name
- Compliance = Rows that pass ÷ Rows checked × 100
- Usual mistake
- The repeated Name is failed on one row only. Both rows that use it fail.
- At work
- Asset data is checked against the client's requirements before each handover drop, and failed rows go back to their author.
- Rule
- Taking-over is not zero snags. Only an item that is a safety risk or stops the Works being used holds back the certificate.
- How it is built
- Items that prevent taking-over = Open punch items − Minor items listed in the TOC
- Usual mistake
- Every open item was counted. Minor items may be listed in the TOC and finished later.
- At work
- Before the Engineer's inspection the site team brings the punch list up to date and agrees what will be listed in the TOC.
- Rule
- Late means after its own date. Each defect is measured against the date its notice or the TOC gave, not against the DNP expiry.
- How it is built
- DNP expiry = Date of completion + 365 days
- Due date of a defect = Date notified, or the date of completion for TOC items + Days it was given
- Usual mistake
- You measured against the DNP expiry. Each defect has its own remedy date: D-03 and D-07 were late, and D-09 was not.
- At work
- The defects register is kept for the year after taking-over, and the client's team checks every remedy date against it.
- Rule
- Half at taking-over, the rest after the DNP, less what the Employer paid others to remedy.
- How it is built
- Retention released after the TOC = Limit of Retention Money ÷ 2
- Net amount after the DNP = Second half − Engineer's figure for D-08
- Usual mistake
- That is all the Retention Money held. Only the first half is released after the Taking-Over Certificate.
- At work
- At taking-over and again at the end of the DNP the commercial team chases each half of the retention.