Cheat sheet
Site levels: platform, cut and fill, building corners
Every rule of the course on one page: how each figure is built, the mistake people usually make, and where it comes up at work. Print it or keep it open while you work.
- Rule
- One survey, one surface. Every later level and volume is taken from Ground; its range is the fall.
- How it is built
- Fall = Highest level of Ground − Lowest level of Ground
- Usual mistake
- You took the fall across the platform only. The task asks for the whole grid: highest spot level less lowest.
- At work
- Surveyors take spot levels on a grid before design, and every later volume is measured against them.
- Rule
- Balanced as dug is short as placed. Fill less cut × 0.90, both in compacted m3.
- How it is built
- Short = Volume Platform 412, Fill − Volume Platform 412, Cut × 0.90
- Usual mistake
- Cut and fill balance as dug, in bank m3. Placed and compacted, the cut shrinks to 0.90 of its volume: compare compacted with compacted.
- At work
- Earthwork volumes are taken from the ground and design surfaces and confirmed before they are priced.
- Rule
- Balance in compacted m3. √0.90 × (west ground − L) = L − east ground.
- How it is built
- Level L = East ground + √0.90 × west ground ÷ 1 + √0.90
- Usual mistake
- That level balances dug m3, without shrinkage. The cut must be compacted to 0.90 first, so the platform goes a little lower.
- At work
- Designers balance cut and fill with the shrink factor from the soils report before they fix the level.
- Rule
- Fix from the monument, then check. Bearing from north; the setback is the nearest side to the street.
- How it is built
- Setback = N of BC1 to BC2 − N of C1 to C2
- Usual mistake
- That is the setback of the platform edge. The rule applies to the building: take the side BC1 to BC2.
- At work
- Setting-out surveyors fix primary corners from boundary monuments and check them against the plot rules.
- Rule
- Decide every stake. d = √(dE² + dN²) against 10 mm; one diagonal checks the shape.
- How it is built
- Diagonal error = Measured BC2 to BC4 − Design diagonal
- Usual mistake
- The size is right, the sign is not. Measured less design: the measured diagonal is shorter, so the error is negative.
- At work
- The surveyor checks each stake against its design and a diagonal before formwork goes up.