Cheat sheet
Site safety: risk, permits, incidents and LTIFR
Every rule of the course on one page: how each figure is built, the mistake people usually make, and where it comes up at work. Print it or keep it open while you work.
- Rule
- The score decides, not the fear. Severity × likelihood gives the tier, and the tier says what happens before work starts.
- How it is built
- Risk Score = Severity × Likelihood
- Usual mistake
- Counted by severity alone. The tier comes from the score, severity × likelihood.
- At work
- The health and safety lead walks the deck with the site manager and the foreman the day before every pour.
- Rule
- Change the hazard if you can; protect everyone before you protect one person. PPE is the last line, never the first.
- How it is built
- OBS-001 residual score = Residual severity × Residual likelihood
- Usual mistake
- The harness option. PPE is the last line; guard rails are higher in the hierarchy and practicable here.
- At work
- Controls are agreed with the site manager and the trade foreman, then checked on the deck before the work.
- Rule
- A permit is for the jobs the rule names, every time. It adds checks before the work; it never replaces the risk assessment.
- How it is built
- Jobs that need a permit = Jobs a rule line names
- Usual mistake
- One permit job missed. Disc cutting is hot work, and taking out a guard rail opens an unprotected edge.
- At work
- Every Monday the look-ahead is checked against the permit rule and the permits are prepared before the jobs start.
- Rule
- Investigate a near miss like an injury, with the people who do the work. Fix the system that let it happen, then reassess.
- How it is built
- OBS-004 residual score = Residual severity × Residual likelihood
- Usual mistake
- The briefing option. The loading gate is an engineering control, higher in the hierarchy.
- At work
- The incident is investigated within a day with the gang, and the fix is presented at the next morning's toolbox talk.
- Rule
- Lost time is a missed shift, and the rate runs over the same hours as the count. Report the events behind the rate too.
- How it is built
- LTIFR, project to date = Lost-time injuries × 1,000,000 ÷ Hours worked
- Usual mistake
- INC-004 counted. No scheduled shift was missed: the weekend is not a working day.
- At work
- Each month the lead reconciles the incident log with the gate hours and sends both with the progress report.