Site safety: risk, permits, incidents and LTIFR

Every rule of the course on one page: how each figure is built, the mistake people usually make, and where it comes up at work. Print it or keep it open while you work.

Task 1

Risk before the pour: severity times likelihood

Theory (7 min)
Rule
The score decides, not the fear. Severity × likelihood gives the tier, and the tier says what happens before work starts.
How it is built
  • Risk Score = Severity × Likelihood
Usual mistake
Counted by severity alone. The tier comes from the score, severity × likelihood.
At work
The health and safety lead walks the deck with the site manager and the foreman the day before every pour.

Task 2

The hierarchy of controls and residual risk

Theory (8 min)
Rule
Change the hazard if you can; protect everyone before you protect one person. PPE is the last line, never the first.
How it is built
  • OBS-001 residual score = Residual severity × Residual likelihood
Usual mistake
The harness option. PPE is the last line; guard rails are higher in the hierarchy and practicable here.
At work
Controls are agreed with the site manager and the trade foreman, then checked on the deck before the work.

Task 3

Permits to work for the week

Theory (7 min)
Rule
A permit is for the jobs the rule names, every time. It adds checks before the work; it never replaces the risk assessment.
How it is built
  • Jobs that need a permit = Jobs a rule line names
Usual mistake
One permit job missed. Disc cutting is hot work, and taking out a guard rail opens an unprotected edge.
At work
Every Monday the look-ahead is checked against the permit rule and the permits are prepared before the jobs start.

Task 4

A near miss, its investigation and the toolbox talk

Theory (8 min)
Rule
Investigate a near miss like an injury, with the people who do the work. Fix the system that let it happen, then reassess.
How it is built
  • OBS-004 residual score = Residual severity × Residual likelihood
Usual mistake
The briefing option. The loading gate is an engineering control, higher in the hierarchy.
At work
The incident is investigated within a day with the gang, and the fix is presented at the next morning's toolbox talk.

Task 5

Lost time and the LTIFR for the client's report

Theory (9 min)
Rule
Lost time is a missed shift, and the rate runs over the same hours as the count. Report the events behind the rate too.
How it is built
  • LTIFR, project to date = Lost-time injuries × 1,000,000 ÷ Hours worked
Usual mistake
INC-004 counted. No scheduled shift was missed: the weekend is not a working day.
At work
Each month the lead reconciles the incident log with the gate hours and sends both with the progress report.