Cheat sheet
Sand stockpile: survey, tonnes and the tickets
Every rule of the course on one page: how each figure is built, the mistake people usually make, and where it comes up at work. Print it or keep it open while you work.
- Rule
- A heap is the space between two surfaces. Pile surface from the rover points, minus the ground before tipping.
- How it is built
- Pile volume = Volume of the survey
- Usual mistake
- That is a box over the toe. The sides slope at 1:1.5, so the heap holds about half of it: read the survey's Volume.
- At work
- Site surveyors measure stockpiles with a rover or a drone each month, against the base surveyed before tipping.
- Rule
- A heap is loose. Tonnes = volume × the mean loose bulk density of the samples.
- How it is built
- Tonnes over-stated = Tonnes at 1.60 − Tonnes of the second survey
- Usual mistake
- You used sample 2 alone. Take the mean of the three samples, to 0.01 t/m3.
- At work
- The site lab runs loose bulk density tests on delivered aggregate and the surveyor uses their mean.
- Rule
- Green is not proof. Remove the duplicated ticket once, then total the genuine ones.
- How it is built
- Genuine tickets = Tickets not rejected, net tonnes
- Usual mistake
- That still counts the duplicate. Reject the second SS-0418 entry, then read Hauled again.
- At work
- Tickets are reconciled against the survey before the supplier's invoice is approved.
- Rule
- The book follows the measurement; the money follows the cause. Adjust to the survey, deduct the duplicated load.
- How it is built
- Invoice deduction = Duplicated ticket × Price per tonne
- Usual mistake
- You charged the whole variance. Part of it is density and survey; the supplier owes the one duplicated load.
- At work
- The surveyor proposes the stock adjustment; the site manager confirms it and deducts the duplicate from the invoice.