Cheat sheet

Sand stockpile: survey, tonnes and the tickets

Every rule of the course on one page: how each figure is built, the mistake people usually make, and where it comes up at work. Print it or keep it open while you work.

Task 1

One heap, one volume

Theory (6 min)
Rule
A heap is the space between two surfaces. Pile surface from the rover points, minus the ground before tipping.
How it is built
  • Pile volume = Volume of the survey
Usual mistake
That is a box over the toe. The sides slope at 1:1.5, so the heap holds about half of it: read the survey's Volume.
At work
Site surveyors measure stockpiles with a rover or a drone each month, against the base surveyed before tipping.

Task 2

Density turns cubic metres into tonnes

Theory (6 min)
Rule
A heap is loose. Tonnes = volume × the mean loose bulk density of the samples.
How it is built
  • Tonnes over-stated = Tonnes at 1.60 − Tonnes of the second survey
Usual mistake
You used sample 2 alone. Take the mean of the three samples, to 0.01 t/m3.
At work
The site lab runs loose bulk density tests on delivered aggregate and the surveyor uses their mean.

Task 3

Tickets against the heap

Theory (6 min)
Rule
Green is not proof. Remove the duplicated ticket once, then total the genuine ones.
How it is built
  • Genuine tickets = Tickets not rejected, net tonnes
Usual mistake
That still counts the duplicate. Reject the second SS-0418 entry, then read Hauled again.
At work
Tickets are reconciled against the survey before the supplier's invoice is approved.

Task 4

Close the gap: adjust the book, charge the supplier

Theory (6 min)
Rule
The book follows the measurement; the money follows the cause. Adjust to the survey, deduct the duplicated load.
How it is built
  • Invoice deduction = Duplicated ticket × Price per tonne
Usual mistake
You charged the whole variance. Part of it is density and survey; the supplier owes the one duplicated load.
At work
The surveyor proposes the stock adjustment; the site manager confirms it and deducts the duplicate from the invoice.