Cheat sheet

Price, win and vary a FIDIC contract

Every rule of the course on one page: how each figure is built, the mistake people usually make, and where it comes up at work. Print it or keep it open while you work.

Task 1

Price the two blank lines before the tender closes

Theory (7 min)
Rule
Every measured line needs a rate. Rates in the bill stay net.
How it is built
  • Internal walls section, net = INT.01 total + INT.02 total
Usual mistake
That is INT.01 alone. The section also holds INT.02, the blockwork to the core.
At work
On tender morning the estimator runs down the bill for any line still without a rate.

Task 2

Put the mark-ups on once: the tender sum

Theory (8 min)
Rule
Mark-ups go on once, over the whole bill, each on the total above it.
How it is built
  • Tender sum = Direct cost of the bill + Head office overheads + Risk allowance + Profit
Usual mistake
You added the three percentages and took them on the net cost once. Each mark-up sits on the running total above it.
At work
The director signs the tender only after checking each mark-up row and its base.

Task 3

Level the drywall bids before you award

Theory (8 min)
Rule
Plug the gap on your sheet, at the highest rate another bidder quoted. Award the lowest complete bid.
How it is built
  • Bidder B leveled = Bidder B as recorded + PT-01 quantity × plug rate
Usual mistake
You plugged PT-01 at B's own rate for the flats. B never priced shops and offices; the rule is the highest rate another bidder quoted.
At work
Before any subcontract is let, the commercial manager wants every bid on one scope.

Task 4

Interim Payment 1: value May, know the retention limit

Theory (8 min)
Rule
10 % comes off every month until the limit. The limit is one figure for the whole Contract.
How it is built
  • Net due = Gross valuation − Retention
  • Retention limit = Accepted Contract Amount × 5 %
Usual mistake
That is 10 % of the Accepted Contract Amount. 10 % is the rate per valuation; the limit is 5 %.
At work
At each month end the contractor's QS sends the Statement and tracks the 28-day and 56-day clocks.

Task 5

The first variation, at the rates of the Contract

Theory (8 min)
Rule
Similar work takes the rate of the Contract: the net bill rate with the tender mark-ups.
How it is built
  • Variation value = Quantity × net rate + Overheads + Risk + Profit
Usual mistake
That is the quantity at the net rate. The rate of the Contract carries the tender mark-ups too.
At work
Within 28 days of an instruction the QS sends the Engineer the particulars and a valued proposal.