Cheat sheet
Price, win and vary a FIDIC contract
Every rule of the course on one page: how each figure is built, the mistake people usually make, and where it comes up at work. Print it or keep it open while you work.
- Rule
- Every measured line needs a rate. Rates in the bill stay net.
- How it is built
- Internal walls section, net = INT.01 total + INT.02 total
- Usual mistake
- That is INT.01 alone. The section also holds INT.02, the blockwork to the core.
- At work
- On tender morning the estimator runs down the bill for any line still without a rate.
- Rule
- Mark-ups go on once, over the whole bill, each on the total above it.
- How it is built
- Tender sum = Direct cost of the bill + Head office overheads + Risk allowance + Profit
- Usual mistake
- You added the three percentages and took them on the net cost once. Each mark-up sits on the running total above it.
- At work
- The director signs the tender only after checking each mark-up row and its base.
- Rule
- Plug the gap on your sheet, at the highest rate another bidder quoted. Award the lowest complete bid.
- How it is built
- Bidder B leveled = Bidder B as recorded + PT-01 quantity × plug rate
- Usual mistake
- You plugged PT-01 at B's own rate for the flats. B never priced shops and offices; the rule is the highest rate another bidder quoted.
- At work
- Before any subcontract is let, the commercial manager wants every bid on one scope.
- Rule
- 10 % comes off every month until the limit. The limit is one figure for the whole Contract.
- How it is built
- Net due = Gross valuation − Retention
- Retention limit = Accepted Contract Amount × 5 %
- Usual mistake
- That is 10 % of the Accepted Contract Amount. 10 % is the rate per valuation; the limit is 5 %.
- At work
- At each month end the contractor's QS sends the Statement and tracks the 28-day and 56-day clocks.
- Rule
- Similar work takes the rate of the Contract: the net bill rate with the tender mark-ups.
- How it is built
- Variation value = Quantity × net rate + Overheads + Risk + Profit
- Usual mistake
- That is the quantity at the net rate. The rate of the Contract carries the tender mark-ups too.
- At work
- Within 28 days of an instruction the QS sends the Engineer the particulars and a valued proposal.