Cheat sheet
Quantity takeoff from PDF, DWG and IFC
Every rule of the course on one page: how each figure is built, the mistake people usually make, and where it comes up at work. Print it or keep it open while you work.
- Rule
- A scale belongs to a paper size. Calibrate on the 40000 dimension; then area × 0.200 m.
- How it is built
- Ground slab concrete = Slab edge area × 0.200 m
- Usual mistake
- That is a quarter of the slab. The ERP read 1:100 from the title block, but the A3 page is at 1:200. Calibrate on the 40000 dimension.
- At work
- Cost consultants receive drawings as PDFs at any size; calibration on a figured dimension is the first click.
- Rule
- One face, built height, big openings out. P1 length × 3.05 m, less openings over 1.00 m2.
- How it is built
- Level 1 partitions = Centreline length, group P1 L1 × 3.05 − D1 doors
- Usual mistake
- The height stops at the ceiling. P1 runs to the slab soffit, 3.05 m clear, as the note on A-101 says.
- At work
- Partitions are traced as centrelines in groups, then turned into areas by the bill's rule.
- Rule
- Measure over small voids. The core comes off every slab; the 0.48 m2 risers stay in.
- How it is built
- Suspended slab concrete = Slab edge − Core opening × 0.250 × 6
- Usual mistake
- The risers came off. Each is 0.48 m2, under the 1.00 m2 limit: the slab is measured over them.
- At work
- Structural slabs are measured from CAD by layer, with the openings tested against the bill's limit.
- Rule
- The model knows geometry, not the rules. Columns go in the bill between slabs; explain the gap.
- How it is built
- Gap = NetVolume, group Columns − Column concrete
- Usual mistake
- That is the model's NetVolume. It runs through the slabs, which FRM.02 already measured: bill columns between slabs.
- At work
- Model quantities are checked against the bill's rules before they are trusted.
- Rule
- Net in the bill, waste in the rate. The order is the net area × 4 m2 of board × 1.08.
- How it is built
- Board to order = Quantity in your bill × 4 × 1.08
- Usual mistake
- That is the board fixed, with no cutting waste. The order carries the 8 %.
- At work
- The bill goes to the bidders net; the buyer orders from the build-up of the rate.