Въведение в курса · 3 мин

Калкулиране на ОВК и електро: количествени сметки, ценообразуване и офертата (САЩ)

Harwick Medical Office · Two-storey outpatient building, Texas · Измислен проект

You are the estimator at the mechanical, electrical and plumbing (MEP) subcontractor, the firm that installs the building's services: you work out what the job will cost and what to bid. In six tasks you take a medical office in Texas from the drawings to a lump-sum bid, one fixed price for the whole MEP package, to the general contractor (GC), then price the first change order after the award.

Започнете задача 1

Building
Two-storey medical office, 24,000 sf
Contract
Lump-sum MEP subcontract to the general contractor (one fixed price)
Story
March to July 2026
Работа в ERP
Задачи: 6, около 3 ч 37 мин

Кой какво предава на кого

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Идва при вас

  • General contractorGeneral contractor
    • Drawings and bid formЗадача 1
    • Bulletin 2, answering RFI 14Задача 6
  • Controls and balancing firmsYour sub-subcontractors
    • Quotes, tax already inЗадача 5
ВиеEstimator, MEP subcontractor

Тръгва от вас

    • MEP bidЗадача 5
    • Change orderЗадача 6
    General contractorReceives your price
    • Labor hours they are budgetedЗадача 3
    Your field crewsElectricians, sheet metal, pipefitters

Вашият път през проекта

Four tasks turn drawings into quantities and direct cost, one builds the bid, one prices a change after the award. Start with task 1: in the Bill of Quantities you count the devices on the Level 1 electrical plan; task 2 measures conduit and wire for one circuit.

  1. Takeoff and pricing

    Задача 1 · 12 мин

    Електро количества: броене на устройствата

    Вашият резултат
    Device counts for the exam wing
    Документ
    Level 1 electrical plan, exam wing
    В ERP
    Bill of Quantities
  2. Takeoff and pricing

    Задача 2 · 25 мин

    Електро количества: тръба и проводник за верига A-7

    Вашият резултат
    Conduit and wire for one circuit
    Документ
    Circuit A-7 runs and heights
    В ERP
    Bill of Quantities
  3. Takeoff and pricing

    Задача 3 · 45 мин

    Остойностяване на електроинсталациите с разходни норми за труд

    Вашият резултат
    Electrical unit rates and the labor hours
    Документ
    Labor units (hours per item) and the crew rate
    В ERP
    Bill of Quantities
  4. Takeoff and pricing

    Задача 4 · 45 мин

    Въздуховоди: тегло по дебелина (gauge)

    Вашият резултат
    Supply trunk weight and its price
    Документ
    Duct layout, trunk TR-1
    В ERP
    Bill of Quantities
  5. The bid

    Задача 5 · 50 мин

    Съставяне на офертата за MEP: допълнителни разходи за труд, данъци, надценки, bond

    Вашият резултат
    The bid price to the general contractor
    Документ
    Bid terms, tax rule, quotes from sub-subcontractors
    В ERP
    Bill of Quantities, Markups
  6. After award

    Задача 6 · 40 мин

    Оценете заповедта за промяна от RFI 14

    Вашият резултат
    The change order, approved and completed
    Документ
    Bulletin 2 and the change terms
    В ERP
    Variations

How a drawing becomes a bid

Each step below is one task, in the order the money is built. Task 4 does for the ductwork what tasks 1 to 3 do for the electrical.

Counts and lengths
Задача 1QuantitiesCount devices (outlets, switches, lights), measure conduit, the pipe the wire runs in, with its rise and drops, then wire.
MaterialLabor at base wage
Задача 3Direct costHours times crew rate, plus material, line by line.
Overhead, profit, bondBurden, tools, taxMaterialLabor
Задача 5Bid priceBurden (payroll taxes and insurance), tools and tax as lines; overhead, profit and bond on top, in order.
Change orderBid price
Задача 6Change orderAdds less deducts at bid rates, then the change terms once.

В синьо е това, което задачата добавя; в сиво е пренесеното отпреди.

Накратко. Hours are not dollars. Each layer has its own base. Net the change before you mark it up.